8025 N LOUISE AVE 91325

Certificate Information: 8025 N LOUISE AVE 91325

Application / Permit
22014-30000-03401
Plan Check / Job No.
B22WL02684
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of the existing detached garage into an ADU.
Permit Issued
Issued on 8/26/2022
Issuing Office
Current Status
CofO Issued on 12/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2022 APPLICANT
Assigned to Plan Check Engineer 7/18/2022 RICHARD GARCIA
Corrections Issued 7/19/2022 RICHARD GARCIA
Plan Check Approved 8/16/2022 RICHARD GARCIA
Issued 8/26/2022 APPLICANT
Building Plans Picked Up 11/23/2022 APPLICANT
CofO in Progress 10/27/2023 RAUL OLAGI
Permit Finaled 12/1/2023 RUBEN SALAS
CofO Issued 12/1/2023 RUBEN SALAS
Permit Finaled 12/1/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/4/2022 MEGAN GODINEZ
Sewer availability Cleared 8/4/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/5/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 8/5/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 8/5/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 8/5/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/4/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/10/2023 Approved RAUL OLAGI
PLUMBING-Rough 5/26/2023 Not Ready for Inspection RAUL OLAGI
Sewer 5/26/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 5/31/2023 Approved RAUL OLAGI
Sewer 5/31/2023 Approved RAUL OLAGI
Underground Mechanical 5/31/2023 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 7/3/2023 Approved RAUL OLAGI
HVAC-Rough 7/3/2023 Not Ready for Inspection RAUL OLAGI
Underground Mechanical 7/3/2023 Approved RAUL OLAGI
Insulation 7/19/2023 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 8/18/2023 Partial Approval RAUL OLAGI
Green Building Rough 8/18/2023 Approved RAUL OLAGI
HVAC-Rough 8/18/2023 Approved RAUL OLAGI
Insulation 8/18/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 8/18/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 8/29/2023 Approved RAUL OLAGI
Drywall Nailing 9/5/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 9/5/2023 Approved RAUL OLAGI
Final 10/20/2023 Corrections Issued RAUL OLAGI
Green Building Final 10/20/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 10/20/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 10/20/2023 Approved RAUL OLAGI
Final 10/27/2023 OK to Issue CofO RAUL OLAGI