6000 W 75TH ST 90045
Certificate Information: 6000 W 75TH ST 90045
- Application / Permit
- 22014-30000-03381
- Plan Check / Job No.
- B22WL02675
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add (32 sf) laundry room at 1st floor and add (53 sf) at 2nd floor to relocate interior staircase and remodel (e) 2-story SFD
- Permit Issued
- Issued on 11/23/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | FELIPE HERNANDEZ |
| Corrections Issued | 8/8/2022 | FELIPE HERNANDEZ |
| Quality Review Completed | 8/17/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 8/18/2022 | APPLICANT |
| Plan Check Approved | 11/23/2022 | REZA HAGHIGHAT |
| Issued | 11/23/2022 | APPLICANT |
| CofO in Progress | 6/6/2024 | BOBBY KEY |
| Permit Finaled | 6/15/2024 | DANIEL ORRANTE |
| CofO Issued | 6/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/15/2022 | DINAH GARIN |
| Sewer availability | Cleared | 9/15/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 11/23/2022 | FELIPE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 9/28/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 10/13/2023 | Corrections Issued | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 10/13/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 10/13/2023 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 10/13/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 10/18/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 10/18/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 10/18/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 10/24/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 10/24/2023 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 10/30/2023 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 10/30/2023 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 10/30/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 10/30/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 10/30/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 11/22/2023 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 11/22/2023 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 11/22/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 11/22/2023 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 12/7/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 12/7/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 12/7/2023 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 12/11/2023 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 12/11/2023 | Partial Approval | BOBBY KEY |
| Green Building Rough | 12/11/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 12/11/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 12/15/2023 | Conditional Approval | BOBBY KEY |
| Green Building Rough | 12/15/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/15/2023 | Partial Approval | BOBBY KEY |
| Insulation | 12/21/2023 | Corrections Issued | BOBBY KEY |
| Insulation | 12/28/2023 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 12/28/2023 | Partial Approval | BOBBY KEY |
| Insulation | 1/26/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 1/26/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/9/2024 | Conditional Approval | BOBBY KEY |
| Drywall Nailing | 2/9/2024 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 2/9/2024 | Approved | BOBBY KEY |
| Shower Pan | 2/9/2024 | Corrections Issued | BOBBY KEY |
| Shower Pan | 2/12/2024 | Approved | BOBBY KEY |
| Service/Power Release | 4/17/2024 | Not Required | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/6/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 5/6/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/6/2024 | Corrections Issued | BOBBY KEY |
| Final | 5/6/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 5/6/2024 | Approved | BOBBY KEY |
| HVAC-Final | 5/6/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 5/6/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/6/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 5/6/2024 | Approved | BOBBY KEY |
| Final | 5/15/2024 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Not Ready | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 5/17/2024 | Approved | BOBBY KEY |
| Final | 5/17/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 5/17/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 5/17/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Approved | BOBBY KEY |
| Final | 6/5/2024 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 6/5/2024 | Approved | BOBBY KEY |