206 S SALTAIR AVE 90049

Certificate Information: 206 S SALTAIR AVE 90049

Application / Permit
22014-30000-03300
Plan Check / Job No.
B22WL02609
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Build 2 (N) Trellis Cover Patio at Rear and Side of (E) 2-Story S.F.D w/Attached Garage
Permit Issued
Issued on 9/9/2022
Issuing Office
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 DAVID CASTILLO
Corrections Issued 7/15/2022 DAVID CASTILLO
Applicant returned to address corrections 8/4/2022 DAVID CASTILLO
Plan Check Approved 8/26/2022 DAVID CASTILLO
Issued 9/9/2022 APPLICANT
Building Plans Picked Up 9/14/2022 APPLICANT
CofO in Progress 3/3/2023 OGANES TARAKHCHYAN
Permit Finaled 3/15/2023 DANIEL ORRANTE
CofO Issued 3/15/2023 DANIEL ORRANTE
Permit Finaled 3/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/15/2022 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 8/15/2022 KIRK LINKLATER
Roof/Waste drainage to street Cleared 8/15/2022 ANTHONY MAINEZ

Contact Information

Contractor Pacific Southwest Builders Inc; Lic. No.: 553992-B 703 PIER AVE SUITE B #706      HERMOSA BEACH, CA 90254
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/27/2022 Conditional Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 11/3/2022 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 11/3/2022 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 11/29/2022 Approved KENNETH NAGLE
ELECTRICAL-Rough 11/29/2022 Approved KENNETH NAGLE
Green Building Rough 11/29/2022 Approved KENNETH NAGLE
PLUMBING-Rough 11/29/2022 Approved KENNETH NAGLE
Interior/Exterior Lathing 12/5/2022 Partial Approval CLAYTON GRAHAM
Interior/Exterior Lathing 12/7/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 2/21/2023 Approved OGANES TARAKHCHYAN
Final 2/21/2023 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 2/21/2023 Approved OGANES TARAKHCHYAN
Green Building Final 2/21/2023 Approved OGANES TARAKHCHYAN
HVAC-Final 2/21/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Final 2/21/2023 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 2/21/2023 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 2/21/2023 Approved OGANES TARAKHCHYAN
HVAC-Final 2/27/2023 Approved CARLOS MATAMOROS
PLUMBING-Final 2/27/2023 Approved CARLOS MATAMOROS
ELECTRICAL-Final 2/28/2023 Approved OGANES TARAKHCHYAN
HVAC-Final 2/28/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Final 2/28/2023 Approved OGANES TARAKHCHYAN
Final 3/2/2023 OK to Issue CofO OGANES TARAKHCHYAN