2754-2756 S SYCAMORE AVE 90016

Certificate Information: 2754-2756 S SYCAMORE AVE 90016

Application / Permit
22014-30000-03297
Plan Check / Job No.
B22WL02606
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Addition to the front and remodel of (E) Duplex. Per engineering design.
Permit Issued
Issued on 12/16/2022
Issuing Office
West Los Angeles
Current Status
CofO in Progress on 3/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/1/2022 APPLICANT
Assigned to Plan Check Engineer 7/11/2022 ALFREDO JARA
Corrections Issued 7/12/2022 ALFREDO JARA
Applicant returned to address corrections 9/1/2022 JAHANSHAH POURHASSAN
Applicant returned to address corrections 9/6/2022 ALFREDO JARA
Applicant returned to address corrections 10/4/2022 ALFREDO JARA
Building Plans Picked Up 10/6/2022 APPLICANT
Applicant returned to address corrections 10/31/2022 ALFREDO JARA
Plan Check Approved 11/17/2022 EDWIN ESPIN
Issued 12/16/2022 APPLICANT
CofO in Progress 2/24/2025 ARTHUR NEGRETE
No Progress 3/30/2025 DEROLD HAUFF
CofO in Progress 3/30/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/12/2022 TREVOR QUAN
Sewer availability Cleared 8/12/2022 TREVOR QUAN
Tenant Habitability Plan Cleared 8/12/2022 RICARDO BOHORQUEZ
Eng Process Fee Ord 176,300 Cleared 8/18/2022 TREVOR QUAN

Contact Information

Contractor Beton Construction Inc; Lic. No.: 739823-B 13024 SKY VALLEY RD      LOS ANGELES, CA 90049

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/26/2023 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 5/2/2023 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Partial Approval JOSE AVILA
ELECTRICAL-Rough 11/30/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 11/30/2023 Approved JOSE AVILA
HVAC-Rough 12/8/2023 Approved RONNIE MINDANAO
Interior/Exterior Lathing 12/22/2023 Not Ready for Inspection SABAS ALONSO
Wood Frame 12/22/2023 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 1/2/2024 Approved BRENDAN MORELLI
Green Building Rough 1/2/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 1/2/2024 Partial Approval BRENDAN MORELLI
Insulation 1/11/2024 Approved RONNIE MINDANAO
Drywall Nailing 1/18/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 2/29/2024 Partial Approval STUART CHAPMAN
Shower Pan 2/29/2024 Approved STUART CHAPMAN
ELECTRICAL-Final 5/17/2024 Not Ready for Inspection ARTHUR NEGRETE
Final 5/17/2024 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 5/17/2024 Approved ARTHUR NEGRETE
HVAC-Final 5/17/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 5/17/2024 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 5/17/2024 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 5/17/2024 Not Ready for Inspection ARTHUR NEGRETE
Smoke Detectors 5/17/2024 Approved ARTHUR NEGRETE
Service/Power Release 6/24/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 6/28/2024 Approved ARTHUR NEGRETE
Final 2/21/2025 OK to Issue CofO ARTHUR NEGRETE