2902 S WEST BLVD 90016
Certificate Information: 2902 S WEST BLVD 90016
- Application / Permit
- 22014-30000-03286
- Plan Check / Job No.
- B22WL02595
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (E) Duplex remodel and addtion: Addition unit 1 = 376 sf to create new master bedroom, closet and master bathroom Addition unit 2 = 350 sf to create new master bedroom, closet and master bathroom per eingineer's calcs & dwgs.
- Permit Issued
- Issued on 9/23/2022
- Issuing Office
- Current Status
- CofO Issued on 4/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2022 | EDWIN ESPIN |
| Corrections Issued | 7/19/2022 | EDWIN ESPIN |
| Plan Check Approved | 9/12/2022 | EDWIN ESPIN |
| Issued | 9/23/2022 | APPLICANT |
| Building Plans Picked Up | 9/27/2022 | APPLICANT |
| CofO in Progress | 4/15/2025 | ENRIQUE MIRELES |
| No Progress | 4/16/2025 | RAUL BARAJAS |
| CofO in Progress | 4/16/2025 | RAUL BARAJAS |
| Permit Finaled | 4/25/2025 | DEROLD HAUFF |
| Permit Finaled | 4/25/2025 | DEROLD HAUFF |
| CofO Issued | 4/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/20/2022 | STEVE MELGAR |
| Tenant Habitability Plan | Cleared | 8/24/2022 | ISMAEL HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2022 | STEVE MELGAR |
| Low Impact Development | Cleared | 9/2/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/7/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/6/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 10/6/2022 | Partial Approval | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 10/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 10/12/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/17/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/27/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 10/27/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/1/2022 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 11/1/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 11/1/2022 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/2/2022 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2022 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 12/2/2022 | Partial Inspection | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2023 | Partial Approval | CALEB MEISTER |
| Green Building Rough | 1/3/2023 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 1/3/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 1/11/2023 | Corrections Issued | CALEB MEISTER |
| HVAC-Rough | 1/11/2023 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 1/11/2023 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 1/11/2023 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Rough | 2/8/2023 | Corrections Issued | CALEB MEISTER |
| HVAC-Rough | 2/8/2023 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 2/8/2023 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Rough | 2/22/2023 | Approved | CALEB MEISTER |
| HVAC-Rough | 2/22/2023 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 2/22/2023 | Approved | CALEB MEISTER |
| Wood Frame | 2/22/2023 | Approved | CALEB MEISTER |
| Insulation | 3/3/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 3/9/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/3/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 9/12/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 9/12/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 9/12/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 9/12/2023 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 9/12/2023 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 10/6/2023 | Approved | CALEB MEISTER |
| Final | 10/6/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Final | 10/6/2023 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Approved | CALEB MEISTER |
| ELECTRICAL-Final | 11/21/2023 | Approved | STUART CHAPMAN |
| Final | 11/21/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 11/21/2023 | Approved | STUART CHAPMAN |
| HVAC-Final | 11/21/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 11/21/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 11/29/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 11/29/2023 | Corrections Issued | JUSTIN HAWLEY |
| HVAC-Final | 11/29/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 11/29/2023 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 3/6/2024 | Corrections Issued | JUSTIN HAWLEY |
| Service/Power Release | 3/6/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Final | 3/7/2025 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 3/7/2025 | Approved | ENRIQUE MIRELES |
| Final | 4/10/2025 | OK to Issue CofO | ENRIQUE MIRELES |