11964 W MODJESKA PL 90066
Certificate Information: 11964 W MODJESKA PL 90066
- Application / Permit
- 22014-30000-03160
- Plan Check / Job No.
- B22WL02504
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 2-story addition (691 sf) to (e) 2-story SFD (3,312 sf) w./ att. 2-car garage (455 sf) w./ att. trellised roof patio cover (460 sf)
- Permit Issued
- Issued on 10/19/2022
- Issuing Office
- Current Status
- CofO Issued on 10/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | REZA HAGHIGHAT |
| Corrections Issued | 7/10/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 7/20/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 10/4/2022 | APPLICANT |
| Plan Check Approved | 10/17/2022 | REZA HAGHIGHAT |
| Issued | 10/19/2022 | APPLICANT |
| Permit Finaled | 10/24/2024 | CLAUDIO MORENO |
| CofO Issued | 10/24/2024 | CLAUDIO MORENO |
| Permit Finaled | 10/24/2024 | CLAUDIO MORENO |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 7/27/2022 | ADALBERTO VERA |
| Permit | Cleared | 8/15/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 8/16/2022 | CATHERINE ADROVER |
| Low Impact Development | Cleared | 8/26/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 9/7/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 9/21/2022 | PEDRO AYALA |
| GPI Written Notices | Cleared | 9/29/2022 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 9/29/2022 | REZA HAGHIGHAT |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Southland Building & Remodel Company; Lic. No.: 894311-B | 1324 WEST ROSECRANS AVENUE COMPTON, CA 90222 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/23/2023 | Partial Approval | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 2/3/2023 | Partial Approval | RYAN BARNES |
| Deputy Drilled-In Anchors | 2/7/2023 | Approved | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Approved | RYAN BARNES |
| Footing/Foundation/Slab | 2/8/2023 | Approved | RYAN BARNES |
| Deputy Steel/Welding | 2/27/2023 | Conditional Approval | JOHN MATTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Partial Approval | RYAN BARNES |
| Deputy Wood Construction | 5/24/2023 | Approved | RYAN BARNES |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Approved | RYAN BARNES |
| HVAC-Rough | 5/24/2023 | Partial Approval | RYAN BARNES |
| ELECTRICAL-Rough | 6/6/2023 | Approved | RYAN BARNES |
| Green Building Final | 6/6/2023 | Not Ready for Inspection | RYAN BARNES |
| HVAC-Rough | 6/6/2023 | Approved | RYAN BARNES |
| PLUMBING-Rough | 6/6/2023 | Corrections Issued | RYAN BARNES |
| Insulation | 7/13/2023 | Approved | JOHN MATTILLO |
| Shower Pan | 8/4/2023 | Approved | RYAN BARNES |
| Drywall Nailing | 8/11/2023 | Approved | JEREMY TODD |
| Green Building Rough | 8/11/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 8/11/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 4/10/2024 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 4/10/2024 | Approved | RYAN BARNES |
| Final | 4/10/2024 | Conditional Approval | RYAN BARNES |
| Green Building Final | 4/10/2024 | Approved | RYAN BARNES |
| HVAC-Final | 4/10/2024 | Approved | RYAN BARNES |
| PLUMBING-Final | 4/10/2024 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Approved | RYAN BARNES |
| Smoke Detectors | 4/10/2024 | Approved | RYAN BARNES |
| Service/Power Release | 4/26/2024 | Approved | RYAN BARNES |