725 N ALMA REAL DR 90272

Certificate Information: 725 N ALMA REAL DR 90272

Application / Permit
22014-30000-03122
Plan Check / Job No.
B22WL02477
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
proposed addition and renovation of (e) 1-story S.F.R. w/ attached 2-car garage, (n) roof framing and (n) site work
Permit Issued
Issued on 1/13/2023
Issuing Office
Valley
Current Status
Issued on 1/13/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/27/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 HOOMAN HAJIZADEH
Corrections Issued 7/14/2022 HOOMAN HAJIZADEH
Quality Review Completed 7/21/2022 CHIHARU SUZUKI
Building Plans Picked Up 7/26/2022 APPLICANT
Applicant returned to address corrections 10/12/2022 HOOMAN HAJIZADEH
Applicant returned to address corrections 10/14/2022 HOOMAN HAJIZADEH
Plan Check Approved 11/3/2022 HOOMAN HAJIZADEH
Issued 1/13/2023 APPLICANT

Permit Application Clearance Information

Permit Cleared 7/27/2022 CATHERINE ADROVER
Sewer availability Cleared 7/27/2022 CATHERINE ADROVER
ZI Cleared 7/27/2022 YINGSHI HUANG
Trees in Parkway Cleared 8/2/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 8/19/2022 RUEL COLE
Eng Process Fee Ord 176,300 Cleared 9/7/2022 CATHERINE ADROVER
Low Impact Development Cleared 9/28/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 9/29/2022 CATHERINE ADROVER
GPI Written Notices Cleared 10/14/2022 HOOMAN HAJIZADEH
Grading Pre-Inspection Cleared 10/14/2022 HOOMAN HAJIZADEH

Contact Information

Architect Leshtz,, Harper Halprin; Lic. No.: C34496 9856 VIDOR DRIVE      LOS ANGELES, CA 90035
Contractor J L M Development; Lic. No.: 1025019-B 1301 WEST 35TH PLACE      LOS ANGELES, CA 90007
Engineer Barajas,, Jorge; Lic. No.: L8399 3635 SHADOW GROVE RD      PASADENA, CA 91107
Engineer Galbreath,, Sean; Lic. No.: S5653 600 SOUTH LAKE AVE STE 308      PASADENA, CA 91106

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/10/2023 No Access for Inspection BRENDAN LOONEY
Pre-Inspection 2/14/2023 Approved BRENDAN LOONEY
Deputy Drilled-In Anchors 4/5/2023 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 4/7/2023 Partial Approval KENNETH NAGLE
PLUMBING-Rough 5/19/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Sewer 5/19/2023 Approved GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 5/19/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Insulation 5/31/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Partial Approval EVAN COOPER
Footing/Foundation/Slab 7/12/2023 Approved EVAN COOPER
Deputy Wood Construction 7/20/2023 No Access for Inspection KENNETH NAGLE
ELECTRICAL-Rough 8/2/2023 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 8/8/2023 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 8/21/2023 Approved EVAN COOPER
ELECTRICAL-Rough 8/23/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Partial Approval EVAN COOPER
HVAC-Rough 8/23/2023 Approved EVAN COOPER
Shower Pan 9/8/2023 Approved OGANES TARAKHCHYAN
Wood Frame 9/21/2023 Approved EVAN COOPER
Insulation 9/26/2023 Corrections Issued OGANES TARAKHCHYAN
Insulation 9/27/2023 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 9/29/2023 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/6/2023 Not Ready for Inspection EVAN COOPER
Drywall Nailing 10/6/2023 Not Ready for Inspection EVAN COOPER
Green Building Rough 10/6/2023 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 10/6/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 10/11/2023 Approved EVAN COOPER
Green Building Rough 10/11/2023 Approved EVAN COOPER
Insulation 10/11/2023 Approved EVAN COOPER
Interior/Exterior Lathing 10/11/2023 Partial Approval EVAN COOPER
Drywall Nailing 10/19/2023 Approved ARAM AVEDISIAN
Final 10/30/2024 Not Ready for Inspection EVAN COOPER
Green Building Final 10/30/2024 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/30/2024 SGSOV Not Ready EVAN COOPER
Smoke Detectors 10/30/2024 Not Ready for Inspection EVAN COOPER
Gas Test 11/15/2024 Approved JESUS RODRIGUEZ
Green Building Final 12/5/2024 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/5/2024 SGSOV Not Ready EVAN COOPER
Service/Power Release 12/5/2024 Approved EVAN COOPER
Smoke Detectors 12/5/2024 Approved EVAN COOPER
PLUMBING-Final 12/17/2024 Approved EVAN COOPER
Final 1/2/2025 Corrections Issued EVAN COOPER
Green Building Final 1/2/2025 Approved EVAN COOPER
HVAC-Final 1/2/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/2/2025 SGSOV Approved EVAN COOPER