1525 N UMEO ROAD 90272
Certificate Information: 1525 N UMEO ROAD 90272
- Application / Permit
- 22014-30000-03108
- Plan Check / Job No.
- B22WL02475
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition at 3rd floor (263 sf) to enclose (e) trellised roof patio, enclose (e) covered patio at 1st and 2nd floor and remodel (e) 3-story S.F.D. w./ att. garage
- Permit Issued
- Issued on 6/13/2023
- Issuing Office
- Metro
- Current Status
- Issued on 6/13/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | TARIK SAOUD |
| Corrections Issued | 8/1/2022 | TARIK SAOUD |
| Quality Review Completed | 8/8/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 1/30/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 6/5/2023 | REZA HAGHIGHAT |
| Issued | 6/13/2023 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/22/2022 | TARIK SAOUD |
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2022 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 1/30/2023 | CATHERINE ADROVER |
| Private sewage disp. approval | Cleared | 5/11/2023 | BRIAN MILLER |
Contact Information
| Contractor | Waconah Construction; Lic. No.: 908219-B | 218 STEPNEY ST INGLEWOOD, CA 90302 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2024 | Not Ready for Inspection | HERBERT GIRON |
| Deputy Steel/Welding | 2/13/2024 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/8/2024 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 3/14/2024 | Partial Approval | KEVIN SARGSYAN |
| Deputy Steel/Welding | 3/21/2024 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Steel/Welding | 4/25/2024 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 5/16/2024 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/7/2024 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 8/9/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/26/2024 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 8/28/2024 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 9/9/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/24/2024 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 9/25/2024 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 9/25/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/27/2024 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2024 | Partial Approval | EVAN COOPER |
| Green Building Rough | 10/1/2024 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 11/1/2024 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 11/20/2024 | Approved | ARAM AVEDISIAN |
| Shower Pan | 12/3/2024 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 12/6/2024 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 12/6/2024 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/9/2024 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 12/9/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 12/9/2024 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 12/9/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 12/27/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 2/24/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 3/7/2025 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 3/12/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Drywall Nailing | 3/18/2025 | Approved | TEMISTOCLES CAAL |
| Gas Test | 10/6/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 12/16/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 12/17/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 12/24/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 1/7/2026 | Approved | HERBERT GIRON |
| PLUMBING-Final | 1/12/2026 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 1/12/2026 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 2/9/2026 | Approved | KEVIN SARGSYAN |