2114-2116 S MANNING AVE 90025
Certificate Information: 2114-2116 S MANNING AVE 90025
- Application / Permit
- 22014-30000-03090
- Plan Check / Job No.
- B22WL02444
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition (1,215 sf) to (e) 2-story SFD (2570 sf) , add an att. 1-car garage (249 sf) and ADU (799 sf) at first floor per LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 2/21/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/21/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | REZA HAGHIGHAT |
| Corrections Issued | 7/7/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 7/18/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 7/19/2022 | APPLICANT |
| Applicant returned to address corrections | 10/7/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 2/7/2023 | REZA HAGHIGHAT |
| Issued | 2/21/2023 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 8/12/2022 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2022 | JENSON LEE |
| Address approval | Cleared | 12/7/2022 | AHMED AMARRAGY |
| Sewer availability | Cleared | 12/7/2022 | AHMED AMARRAGY |
| Trees in Parkway | Cleared | 12/8/2022 | ADALBERTO VERA |
| Specific Plan | Cleared | 12/19/2022 | PEDRO AYALA |
| Low Impact Development | Cleared | 1/12/2023 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 1/12/2023 | JENSON LEE |
| Permit | Cleared | 1/13/2023 | STEVEN JIN |
| GPI Written Notices | Cleared | 2/7/2023 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 2/7/2023 | REZA HAGHIGHAT |
Contact Information
| Contractor | Shirley David M Construction Corporation; Lic. No.: 602138-B | 2110 MANNING AVENUE LOS ANGELES, CA 90025 |
| Engineer | Shirley,, Peter; Lic. No.: C75050 | 4429 DAWES AVE CULVER CITY, CA 90230 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/14/2023 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Barrier | 4/14/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Subgrade | 4/14/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 5/8/2023 | Corrections Issued | BRENDAN LOONEY |
| METHANE-Barrier | 5/8/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| METHANE-Subgrade | 5/8/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Footing/Foundation/Slab | 5/15/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| METHANE-Barrier | 5/15/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| METHANE-Subgrade | 5/15/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 5/15/2023 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 6/1/2023 | Partial Approval | HERBERT GIRON |
| METHANE-Barrier | 6/1/2023 | Corrections Issued | HERBERT GIRON |
| METHANE-Rough | 6/1/2023 | Corrections Issued | HERBERT GIRON |
| METHANE-Subgrade | 6/1/2023 | Corrections Issued | HERBERT GIRON |
| Underground Mechanical | 6/1/2023 | Partial Approval | HERBERT GIRON |
| METHANE-Barrier | 6/8/2023 | Approved | STEPHANIE SWANSON |
| METHANE-Subgrade | 6/8/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/8/2023 | Approved | STEPHANIE SWANSON |
| Sewer | 6/8/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/16/2023 | Approved | STEPHANIE SWANSON |
| Wood Frame | 6/16/2023 | Partial Approval | STEPHANIE SWANSON |
| Gas Test | 6/22/2023 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 6/22/2023 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2023 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 11/9/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/17/2024 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Rough | 1/17/2024 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 1/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 1/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Rough | 1/19/2024 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 1/19/2024 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 1/19/2024 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 1/22/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/22/2024 | Approved | STEPHANIE SWANSON |
| Deputy Wood Construction | 1/24/2024 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 1/29/2024 | Partial Approval | STEPHANIE SWANSON |
| Green Building Rough | 1/29/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 1/29/2024 | Approved | STEPHANIE SWANSON |
| METHANE-Rough | 1/29/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/29/2024 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 1/29/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 1/29/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/11/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 3/11/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 3/11/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/11/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 3/11/2024 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 3/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 3/14/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 3/18/2024 | Partial Approval | STEPHANIE SWANSON |
| Final | 3/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 3/18/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 3/21/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 3/27/2024 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 8/21/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Final | 8/26/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 8/26/2024 | Corrections Issued | STEPHANIE SWANSON |
| Service/Power Release | 8/26/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Final | 8/27/2024 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 8/27/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 11/6/2024 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 11/6/2024 | SGSOV Not Ready | STEPHANIE SWANSON |
| Final | 11/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 11/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 11/18/2024 | Approved | STEPHANIE SWANSON |
| Final | 12/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 12/17/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 12/17/2024 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 12/17/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 12/17/2024 | Approved | STEPHANIE SWANSON |
| Final | 12/19/2024 | Partial Approval | STEPHANIE SWANSON |