17043 W TENNYSON PL 91344

Certificate Information: 17043 W TENNYSON PL 91344

Application / Permit
22014-30000-03000
Plan Check / Job No.
B22WL02390
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new 1st and 2nd floor addition to (e) S.F.R.
Permit Issued
Issued on 7/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 HOOMAN HAJIZADEH
Corrections Issued 8/8/2022 HOOMAN HAJIZADEH
Quality Review Completed 8/15/2022 CHIHARU SUZUKI
Building Plans Picked Up 8/25/2022 APPLICANT
Plan Check Approved 6/12/2023 KAVIAN REFAHI
Issued 7/14/2023 APPLICANT
CofO in Progress 2/17/2026 STEVEN BACK
No Progress 2/24/2026 STEVEN BACK
CofO in Progress 2/24/2026 STEVEN BACK
CofO in Progress 2/24/2026 STEVEN BACK
Permit Finaled 3/10/2026 JOHN JANSON
CofO Issued 3/10/2026 JOHN JANSON
Permit Finaled 3/10/2026 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/14/2022 COLIN LOREDO
ZI Cleared 12/16/2022 STEVEN WECHSLER
Sewer availability Cleared 12/21/2022 COLIN LOREDO
Watercourse Cleared 1/3/2023 COLIN LOREDO
Low Impact Development Cleared 6/6/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 6/7/2023 ANTHONY MAINEZ
GPI Written Notices Cleared 6/12/2023 HOOMAN HAJIZADEH
Grading Pre-Inspection Cleared 6/12/2023 HOOMAN HAJIZADEH

Contact Information

Contractor Owner-Builder       ,
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/12/2023 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 9/12/2023 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 9/20/2023 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 9/20/2023 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/23/2023 Partial Approval STEVEN BACK
Footing/Foundation/Slab 10/23/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Approved DAVID SCANTLIN
ELECTRICAL-Rough 11/27/2023 Corrections Issued STEVEN BACK
HVAC-Rough 11/27/2023 Corrections Issued STEVEN BACK
PLUMBING-Rough 11/27/2023 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 12/1/2023 Approved STEVEN BACK
HVAC-Rough 12/1/2023 Approved STEVEN BACK
PLUMBING-Rough 12/1/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 12/8/2023 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 Approved DAVID SCANTLIN
Green Building Rough 12/8/2023 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 12/15/2023 Approved CHRIS CHRISTENSEN
Green Building Rough 12/15/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 12/15/2023 Partial Approval CHRIS CHRISTENSEN
Insulation 12/19/2023 Approved CHRIS CHRISTENSEN
Drywall Nailing 12/28/2023 Approved STEVEN BACK
Interior/Exterior Lathing 12/28/2023 Approved STEVEN BACK
ELECTRICAL-Final 8/23/2024 Approved STEVEN BACK
Final 8/23/2024 Corrections Issued STEVEN BACK
Green Building Final 8/23/2024 Approved STEVEN BACK
HVAC-Final 8/23/2024 Not Ready for Inspection STEVEN BACK
PLUMBING-Final 8/23/2024 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/23/2024 SGSOV Approved STEVEN BACK
Smoke Detectors 8/23/2024 Approved STEVEN BACK
Final 2/17/2026 Corrections Issued STEVEN BACK
Final 2/24/2026 Corrections Issued STEVEN BACK
Final 3/6/2026 Conditional Approval STEVEN BACK