408 N ORANGE GROVE AVE 90036
Certificate Information: 408 N ORANGE GROVE AVE 90036
- Application / Permit
- 22014-30000-02945
- Plan Check / Job No.
- B22WL02360
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- build a second story ADU on top of existing garage in existing multi-family property per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 1/18/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | KAVIAN REFAHI |
| Corrections Issued | 7/2/2022 | KAVIAN REFAHI |
| Quality Review Completed | 7/7/2022 | TARIK SAOUD |
| Building Plans Picked Up | 7/14/2022 | APPLICANT |
| Applicant returned to address corrections | 10/31/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 12/6/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 12/12/2022 | KAVIAN REFAHI |
| Plan Check Approved | 1/5/2023 | KAVIAN REFAHI |
| Issued | 1/18/2023 | APPLICANT |
| CofO in Progress | 7/24/2024 | AMIR NAZARIAN |
| Permit Finaled | 7/29/2024 | DEROLD HAUFF |
| CofO Issued | 7/29/2024 | DEROLD HAUFF |
| Permit Finaled | 7/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 7/20/2022 | MAX LODER |
| HPOZ | Cleared | 7/20/2022 | MAX LODER |
| Tenant Habitability Plan | Cleared | 7/20/2022 | MICHAEL SOTO |
| Construction near power lines | Cleared | 7/22/2022 | TINA MIRANDA |
| Address approval | Cleared | 7/25/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 7/26/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 10/20/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/22/2022 | JEANETTE VONG |
Contact Information
| Contractor | Perluss Sheldon K; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/17/2023 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 5/18/2023 | Partial Approval | LILIANA PORTILLO |
| METHANE-Barrier | 5/18/2023 | Approved | LILIANA PORTILLO |
| METHANE-Subgrade | 5/18/2023 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/30/2023 | Corrections Issued | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 7/3/2023 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2023 | Corrections Issued | LILIANA PORTILLO |
| Deputy Wood Construction | 8/4/2023 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 8/30/2023 | Corrections Issued | LILIANA PORTILLO |
| Deputy Wood Construction | 9/21/2023 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Approved | LILIANA PORTILLO |
| Green Building Rough | 11/7/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| METHANE-Rough | 11/7/2023 | Approved | LILIANA PORTILLO |
| Wood Frame | 11/7/2023 | Conditional Approval | LILIANA PORTILLO |
| Insulation | 11/13/2023 | Corrections Issued | LILIANA PORTILLO |
| Special/Order Compliance | 11/13/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 11/20/2023 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/20/2023 | Partial Approval | JOSEPH MCGARRY |
| Final | 2/23/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 2/23/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Green Building Final | 2/23/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Green Building Rough | 2/23/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Smoke Detectors | 2/23/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Special/Order Compliance | 2/23/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 2/23/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Final | 3/28/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 3/28/2024 | Approved | AMIR NAZARIAN |
| Green Building Final | 3/28/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 3/28/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 3/28/2024 | SGSOV Approved | AMIR NAZARIAN |
| Smoke Detectors | 3/28/2024 | Approved | AMIR NAZARIAN |
| Wood Frame | 3/28/2024 | Approved | AMIR NAZARIAN |
| Final | 7/23/2024 | OK to Issue CofO | AMIR NAZARIAN |