408 N ORANGE GROVE AVE 90036

Certificate Information: 408 N ORANGE GROVE AVE 90036

Application / Permit
22014-30000-02945
Plan Check / Job No.
B22WL02360
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
build a second story ADU on top of existing garage in existing multi-family property per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 1/18/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 KAVIAN REFAHI
Corrections Issued 7/2/2022 KAVIAN REFAHI
Quality Review Completed 7/7/2022 TARIK SAOUD
Building Plans Picked Up 7/14/2022 APPLICANT
Applicant returned to address corrections 10/31/2022 KAVIAN REFAHI
Applicant returned to address corrections 12/6/2022 KAVIAN REFAHI
Applicant returned to address corrections 12/12/2022 KAVIAN REFAHI
Plan Check Approved 1/5/2023 KAVIAN REFAHI
Issued 1/18/2023 APPLICANT
CofO in Progress 7/24/2024 AMIR NAZARIAN
Permit Finaled 7/29/2024 DEROLD HAUFF
CofO Issued 7/29/2024 DEROLD HAUFF
Permit Finaled 7/29/2024 DEROLD HAUFF

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 7/20/2022 MAX LODER
HPOZ Cleared 7/20/2022 MAX LODER
Tenant Habitability Plan Cleared 7/20/2022 MICHAEL SOTO
Construction near power lines Cleared 7/22/2022 TINA MIRANDA
Address approval Cleared 7/25/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 7/26/2022 JEANETTE VONG
Sewer availability Cleared 7/26/2022 JEANETTE VONG
Low Impact Development Cleared 10/20/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/22/2022 JEANETTE VONG

Contact Information

Contractor Perluss Sheldon K; Lic. No.: 759817-B 636 NORTH FORMOSA AVENUE      LOS ANGELES, CA 90036
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/17/2023 Approved RICHARD DOCKUS
Footing/Foundation/Slab 5/18/2023 Partial Approval LILIANA PORTILLO
METHANE-Barrier 5/18/2023 Approved LILIANA PORTILLO
METHANE-Subgrade 5/18/2023 Approved LILIANA PORTILLO
Footing/Foundation/Slab 6/30/2023 Corrections Issued LILIANA PORTILLO
Deputy Drilled-In Anchors 7/3/2023 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Corrections Issued LILIANA PORTILLO
Deputy Wood Construction 8/4/2023 Partial Approval SCOTT FINNILA
Wood Frame 8/30/2023 Corrections Issued LILIANA PORTILLO
Deputy Wood Construction 9/21/2023 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Approved LILIANA PORTILLO
Green Building Rough 11/7/2023 Not Ready for Inspection LILIANA PORTILLO
METHANE-Rough 11/7/2023 Approved LILIANA PORTILLO
Wood Frame 11/7/2023 Conditional Approval LILIANA PORTILLO
Insulation 11/13/2023 Corrections Issued LILIANA PORTILLO
Special/Order Compliance 11/13/2023 Approved LILIANA PORTILLO
Drywall Nailing 11/20/2023 Corrections Issued JOSEPH MCGARRY
Interior/Exterior Lathing 11/20/2023 Partial Approval JOSEPH MCGARRY
Final 2/23/2024 Corrections Issued AMIR NAZARIAN
Footing/Foundation/Slab 2/23/2024 Not Ready for Inspection AMIR NAZARIAN
Green Building Final 2/23/2024 Not Ready for Inspection AMIR NAZARIAN
Green Building Rough 2/23/2024 Not Ready for Inspection AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Not Ready AMIR NAZARIAN
Smoke Detectors 2/23/2024 Not Ready for Inspection AMIR NAZARIAN
Special/Order Compliance 2/23/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 2/23/2024 Not Ready for Inspection AMIR NAZARIAN
Final 3/28/2024 Corrections Issued AMIR NAZARIAN
Footing/Foundation/Slab 3/28/2024 Approved AMIR NAZARIAN
Green Building Final 3/28/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 3/28/2024 Approved AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Approved AMIR NAZARIAN
Smoke Detectors 3/28/2024 Approved AMIR NAZARIAN
Wood Frame 3/28/2024 Approved AMIR NAZARIAN
Final 7/23/2024 OK to Issue CofO AMIR NAZARIAN
Green Building Final 7/23/2024 Approved AMIR NAZARIAN