19934 W COVELLO ST 91306
Certificate Information: 19934 W COVELLO ST 91306
- Application / Permit
- 22014-30000-02863
- Plan Check / Job No.
- B22WL02313
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-story addition (268 sf) to (e) single story SFD (1,080 sf)
- Permit Issued
- Issued on 10/14/2022
- Issuing Office
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | REZA HAGHIGHAT |
| Corrections Issued | 6/20/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 7/5/2022 | TARIK SAOUD |
| Building Plans Picked Up | 7/7/2022 | APPLICANT |
| Plan Check Approved | 10/6/2022 | REZA HAGHIGHAT |
| Issued | 10/14/2022 | APPLICANT |
| CofO in Progress | 9/23/2024 | ALEXANDER HANDY |
| Permit Finaled | 6/3/2025 | JOHN JANSON |
| CofO Issued | 6/3/2025 | JOHN JANSON |
| Permit Finaled | 6/3/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2022 | ROMAN GUTIERREZ |
| Permit | Cleared | 9/15/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 9/15/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 9/15/2022 | ROMAN GUTIERREZ |
| Trees in Parkway | Cleared | 10/6/2022 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Djoneva,, Diana Ivanova; Lic. No.: C73805 | 3241 HENRIETTA AVE LA CRESCENTA, CA 91214 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/20/2022 | Approved | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 6/26/2023 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 6/26/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Piling/Pier/Caisson | 6/26/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Footing/Foundation/Slab | 6/30/2023 | Corrections Issued | HORACE FULTZ |
| Underground Mechanical | 7/6/2023 | Not Ready for Inspection | HORACE FULTZ |
| Underground Mechanical | 7/7/2023 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 7/27/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Rough | 7/27/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Underground Mechanical | 7/27/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 9/14/2023 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 9/14/2023 | Approved | ALEXANDER HANDY |
| Structural Steel Frame | 9/14/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Wood Frame | 9/14/2023 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/27/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 9/27/2023 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 9/27/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 9/27/2023 | Partial Approval | ALEXANDER HANDY |
| Shower Pan | 9/27/2023 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 4/30/2024 | Approved | ALEXANDER HANDY |
| Final | 4/30/2024 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 4/30/2024 | Approved | ALEXANDER HANDY |
| Green Building Final | 4/30/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Insulation | 4/30/2024 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/30/2024 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 4/30/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 9/18/2024 | Approved | ALEXANDER HANDY |
| Final | 9/18/2024 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 9/18/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 9/18/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 9/18/2024 | Approved | ALEXANDER HANDY |