2323 S MALCOLM AVE 90064
Certificate Information: 2323 S MALCOLM AVE 90064
- Application / Permit
- 22014-30000-02669
- Plan Check / Job No.
- B22WL02199
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story ADU per state Law (CA Govt. Code 65852.2 (e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d),(g))
- Permit Issued
- Issued on 4/3/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | TARIK SAOUD |
| Corrections Issued | 6/13/2022 | TARIK SAOUD |
| Quality Review Completed | 6/19/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 6/22/2022 | APPLICANT |
| Applicant returned to address corrections | 10/28/2022 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 12/14/2022 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 2/14/2023 | HOOMAN HAJIZADEH |
| Plan Check Approved | 2/28/2023 | HOOMAN HAJIZADEH |
| Issued | 4/3/2023 | APPLICANT |
| CofO in Progress | 5/25/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 6/3/2024 | DANIEL ORRANTE |
| CofO Issued | 6/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/15/2022 | TARIK SAOUD |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2022 | JENSON LEE |
| Sewer availability | Cleared | 7/1/2022 | JENSON LEE |
| Specific Plan | Cleared | 7/7/2022 | EDUARDO HERMOSO |
| Hydrant and Access approval | Cleared | 8/1/2022 | GILBERT URREA |
| Specific Plan | Cleared | 9/6/2022 | KYLE WINSTON |
| Construction near power lines | Cleared | 9/7/2022 | RIDWAN HARDY |
| Address approval | Cleared | 11/2/2022 | JENSON LEE |
| Low Impact Development | Cleared | 11/15/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 2/15/2023 | JENSON LEE |
Contact Information
| Contractor | Bohrer Construction; Lic. No.: 916973-B | 12251 MIRANDA STREET VALLEY VILLAGE, CA 91607 |
| Engineer | Onishi,, Robert K; Lic. No.: S3705 | 4438 LINDBLADE DRIVE LOS ANGELES, CA 90066 |
| Engineer | Yamashita,, Mark Alan; Lic. No.: L7155 | 6718 BIANCA AVE LAKE BALBOA, CA 91406 |
| Geologist | Minas,, Shant; Lic. No.: GEO8859 | 566 RIVERDALE DRIVE GLENDALE, CA 91204 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/18/2023 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 4/20/2023 | Approved | JOHNNY MIRANDA |
| METHANE-Barrier | 4/20/2023 | Approved | JOHNNY MIRANDA |
| METHANE-Subgrade | 4/20/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 4/25/2023 | Partial Approval | HERBERT GIRON |
| Insulation | 4/25/2023 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2023 | Approved | JEREMY TODD |
| Sewer | 6/13/2023 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Rough | 7/20/2023 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2023 | Approved | JESUS PINEDA |
| HVAC-Rough | 7/20/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 7/20/2023 | Approved | JESUS PINEDA |
| HVAC-Rough | 9/6/2023 | Corrections Issued | BEN MOLSTAD |
| Interior/Exterior Lathing | 9/6/2023 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 9/14/2023 | Approved | JESUS PINEDA |
| HVAC-Rough | 9/14/2023 | Conditional Approval | JESUS PINEDA |
| Interior/Exterior Lathing | 9/14/2023 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 9/20/2023 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 9/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 9/29/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 10/5/2023 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 10/18/2023 | Approved | BEN MOLSTAD |
| Shower Pan | 10/18/2023 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 3/5/2024 | Approved | ARAM AVEDISIAN |
| Final | 3/5/2024 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 3/5/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/5/2024 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 3/5/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 5/24/2024 | Approved | TEMISTOCLES CAAL |
| Final | 5/24/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| Green Building Final | 5/24/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 5/24/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 5/24/2024 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 5/24/2024 | Approved | TEMISTOCLES CAAL |