11217 W LAURIE DR 91604
Certificate Information: 11217 W LAURIE DR 91604
- Application / Permit
- 22014-30000-02612
- Plan Check / Job No.
- B22WL02167
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- renovation of existing one story S.F.R. and addition of 626 sf
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | KAVIAN REFAHI |
| Corrections Issued | 7/10/2022 | KAVIAN REFAHI |
| Quality Review Completed | 7/11/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 11/1/2022 | KAVIAN REFAHI |
| Plan Check Approved | 11/30/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 1/6/2023 | APPLICANT |
| No Progress | 5/30/2023 | KAVIAN REFAHI |
| Plan Check Approved | 6/26/2023 | KAVIAN REFAHI |
| Issued | 6/27/2023 | APPLICANT |
| CofO in Progress | 10/8/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 11/19/2025 | RUBEN SALAS |
| CofO Issued | 11/19/2025 | RUBEN SALAS |
| Permit Finaled | 11/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/28/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 7/28/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 7/28/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 7/28/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 8/31/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 9/19/2022 | LAVEON RIDER |
| Low Impact Development | Cleared | 9/30/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/30/2022 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 11/1/2022 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 11/1/2022 | KAVIAN REFAHI |
| Specific Plan | Cleared | 6/2/2023 | OLGA AYALA |
| Specific Plan | Cleared | 6/2/2023 | OLGA AYALA |
| Hydrant and Access approval | Cleared | 6/12/2023 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 6/19/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 6/20/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Farag,, Amgad N; Lic. No.: C74076 | 27050 MAPLE TREE CT VALENCIA, CA 91381 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/5/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 9/14/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/19/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 9/20/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/25/2023 | Partial Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/25/2023 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2023 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 1/2/2024 | Conditional Approval | JUAN VALENZUELA |
| Pre-Inspection | 1/3/2024 | Approved | CHRISTOPHE COCHRAN |
| Pre-Inspection | 3/18/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 4/2/2024 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 4/2/2024 | Approved | JOHN COLEMAN |
| Deputy Steel/Welding | 4/3/2024 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 4/9/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 4/9/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 4/9/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 4/9/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 4/22/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Rough | 4/22/2024 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 4/22/2024 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 4/22/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Shower Pan | 4/24/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 4/24/2024 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 4/29/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Shower Pan | 5/3/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 5/9/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 5/24/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 5/24/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 6/28/2024 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 10/30/2024 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 11/12/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/18/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 9/18/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 9/18/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 9/18/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 9/18/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 10/6/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 10/6/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 10/8/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 10/8/2025 | Approved | CHRISTOPHE COCHRAN |