11217 W LAURIE DR 91604

Certificate Information: 11217 W LAURIE DR 91604

Application / Permit
22014-30000-02612
Plan Check / Job No.
B22WL02167
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
renovation of existing one story S.F.R. and addition of 626 sf
Permit Issued
Issued on 6/27/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 KAVIAN REFAHI
Corrections Issued 7/10/2022 KAVIAN REFAHI
Quality Review Completed 7/11/2022 TARIK SAOUD
Applicant returned to address corrections 11/1/2022 KAVIAN REFAHI
Plan Check Approved 11/30/2022 KAVIAN REFAHI
Building Plans Picked Up 1/6/2023 APPLICANT
No Progress 5/30/2023 KAVIAN REFAHI
Plan Check Approved 6/26/2023 KAVIAN REFAHI
Issued 6/27/2023 APPLICANT
CofO in Progress 10/8/2025 CHRISTOPHE COCHRAN
Permit Finaled 11/19/2025 RUBEN SALAS
CofO Issued 11/19/2025 RUBEN SALAS
Permit Finaled 11/19/2025 RUBEN SALAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/28/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 7/28/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 7/28/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 7/28/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/28/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 8/31/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/19/2022 LAVEON RIDER
Low Impact Development Cleared 9/30/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/30/2022 CARLOS AGUILERA
GPI Written Notices Cleared 11/1/2022 KAVIAN REFAHI
Grading Pre-Inspection Cleared 11/1/2022 KAVIAN REFAHI
Specific Plan Cleared 6/2/2023 OLGA AYALA
Specific Plan Cleared 6/2/2023 OLGA AYALA
Hydrant and Access approval Cleared 6/12/2023 LAVEON RIDER
Low Impact Development (LID) Cleared 6/19/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 6/20/2023 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Farag,, Amgad N; Lic. No.: C74076 27050 MAPLE TREE CT      VALENCIA, CA 91381

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/5/2023 Approved CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 9/14/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/19/2023 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 9/20/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 10/25/2023 Partial Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 10/25/2023 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Partial Approval MICHEL ABAJAN
Deputy Wood Construction 1/2/2024 Conditional Approval JUAN VALENZUELA
Pre-Inspection 1/3/2024 Approved CHRISTOPHE COCHRAN
Pre-Inspection 3/18/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 4/2/2024 Approved JOHN COLEMAN
PLUMBING-Rough 4/2/2024 Approved JOHN COLEMAN
Deputy Steel/Welding 4/3/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 4/9/2024 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 4/9/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 4/9/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 4/9/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/22/2024 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 4/22/2024 Approved CHRISTOPHE COCHRAN
HVAC-Rough 4/22/2024 Approved CHRISTOPHE COCHRAN
Shower Pan 4/22/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Shower Pan 4/24/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Wood Frame 4/24/2024 Approved CHRISTOPHE COCHRAN
Shower Pan 4/29/2024 Corrections Issued CHRISTOPHE COCHRAN
Shower Pan 5/3/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 5/9/2024 Partial Approval CHRISTOPHE COCHRAN
Insulation 5/24/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 5/24/2024 Approved CHRISTOPHE COCHRAN
Drywall Nailing 6/28/2024 Approved CHRISTOPHE COCHRAN
Sewer 10/30/2024 Approved CHRISTOPHE COCHRAN
Underground Mechanical 11/12/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/18/2025 Approved CHRISTOPHE COCHRAN
Final 9/18/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 9/18/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 9/18/2025 Approved CHRISTOPHE COCHRAN
Final 10/6/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 10/6/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 10/8/2025 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 10/8/2025 Approved CHRISTOPHE COCHRAN