10346 W WEDDINGTON ST 91601

Certificate Information: 10346 W WEDDINGTON ST 91601

Application / Permit
22014-30000-02545
Plan Check / Job No.
B22WL02135
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Garage Conversion to ADU and Addition per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 9/7/2022
Issuing Office
Current Status
CofO Issued on 7/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2022 APPLICANT
Assigned to Plan Check Engineer 6/6/2022 EDWIN ESPIN
Corrections Issued 6/7/2022 EDWIN ESPIN
Applicant returned to address corrections 8/26/2022 DAVID CASTILLO
Plan Check Approved 9/6/2022 EDWIN ESPIN
Issued 9/7/2022 APPLICANT
Building Plans Picked Up 9/8/2022 APPLICANT
CofO in Progress 7/6/2023 JENNIFER RABUCHIN
Permit Finaled 7/18/2023 MICHAEL SMITH
CofO Issued 7/18/2023 MICHAEL SMITH
Permit Finaled 7/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/13/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 7/13/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 7/13/2022 MEGAN GODINEZ
Sewer availability Cleared 7/13/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 7/13/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 7/13/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 7/13/2022 MEGAN GODINEZ
Construction near power lines Cleared 8/18/2022 RIDWAN HARDY

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Level + Square Construction Fabrication; Lic. No.: 1046873-B 1714 N ORANGE GROVE AVE      LOS ANGELES, CA 90046

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/7/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 12/7/2022 Partial Approval JOHN HAYES
Underground Mechanical 12/7/2022 Not Ready for Inspection JOHN HAYES
Deputy Drilled-In Anchors 12/9/2022 Conditional Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 12/15/2022 Corrections Issued JOHN HAYES
Deputy Drilled-In Anchors 12/29/2022 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 12/30/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 2/2/2023 Partial Approval JOHN HAYES
ELECTRICAL-Rough 2/2/2023 Not Ready for Inspection JOHN HAYES
Green Building Rough 2/2/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 2/2/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 2/9/2023 Corrections Issued JOHN HAYES
Green Building Rough 2/9/2023 Partial Approval JOHN HAYES
Wood Frame 2/9/2023 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 2/17/2023 Not Ready for Inspection JOHN HAYES
Green Building Rough 2/17/2023 Corrections Issued JOHN HAYES
Rough-Elec/Plmb/HVAC 2/17/2023 Corrections Issued JOHN HAYES
Interior/Exterior Lathing 3/7/2023 Partial Approval JOHN KIDWELL
Insulation 3/16/2023 Corrections Issued JOHN COLEMAN
Drywall Nailing 3/31/2023 Approved JOHN KIDWELL
Green Building Rough 3/31/2023 Approved JOHN KIDWELL
Pre-Inspection 4/26/2023 Approved JENNIFER RABUCHIN
Shower Pan 4/26/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/7/2023 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 6/7/2023 Not Ready for Inspection JENNIFER RABUCHIN
Final 6/7/2023 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 6/7/2023 Approved JENNIFER RABUCHIN
Green Building Final 6/7/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 6/7/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 6/7/2023 Not Ready for Inspection JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/7/2023 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 6/7/2023 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 6/30/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/30/2023 SGSOV Not Ready JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/5/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/5/2023 Approved JENNIFER RABUCHIN
Final 7/5/2023 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 7/5/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/5/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/5/2023 Approved JENNIFER RABUCHIN