158 N VISTA ST 90036

Certificate Information: 158 N VISTA ST 90036

Application / Permit
22014-30000-02430
Plan Check / Job No.
B22WL02006
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion & addition of (E) garage to ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 11/22/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 JASON JANGADA
Corrections Issued 5/27/2022 JASON JANGADA
Applicant returned to address corrections 9/14/2022 JASON JANGADA
Applicant returned to address corrections 10/5/2022 JASON JANGADA
Plan Check Approved 11/22/2022 DAVID CASTILLO
Issued 11/22/2022 APPLICANT
Building Plans Picked Up 11/22/2022 APPLICANT
CofO in Progress 3/29/2024 AMIR NAZARIAN
CofO Issued 4/8/2024 DEROLD HAUFF
Permit Finaled 4/8/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/7/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/8/2022 JEANIE LAM
CPC Cleared 6/9/2022 DANIEL CORONADO
CPC Cleared 6/9/2022 DANIEL CORONADO
Sewer availability Cleared 6/13/2022 JEANIE LAM
HPOZ Cleared 7/28/2022 DANIEL MATA
Construction near power lines Cleared 8/20/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Liu,, Tienkuang; Lic. No.: C40889 4852 RIO HONDO AVE      TEMPLE CITY, CA 91780

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/1/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 7/6/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 7/13/2023 Approved LILIANA PORTILLO
METHANE-Barrier 7/13/2023 Approved LILIANA PORTILLO
METHANE-Subgrade 7/13/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 7/13/2023 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 9/1/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 9/1/2023 Corrections Issued LILIANA PORTILLO
Sewer 9/1/2023 Approved LILIANA PORTILLO
Underground Mechanical 9/1/2023 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 9/6/2023 Partial Approval LILIANA PORTILLO
HVAC-Rough 9/6/2023 Corrections Issued LILIANA PORTILLO
Insulation 9/6/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 9/6/2023 Conditional Approval LILIANA PORTILLO
Underground Mechanical 9/6/2023 Approved LILIANA PORTILLO
ELECTRICAL-Rough 9/11/2023 Approved LILIANA PORTILLO
HVAC-Rough 9/11/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 9/13/2023 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Approved LILIANA PORTILLO
Green Building Rough 9/20/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 9/20/2023 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 10/2/2023 Approved LILIANA PORTILLO
METHANE-Rough 10/2/2023 Approved LILIANA PORTILLO
Insulation 10/3/2023 Approved LILIANA PORTILLO
Drywall Nailing 10/11/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/17/2023 Approved BRENDAN MORELLI
Final 3/14/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 3/14/2024 Not Ready for Inspection AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Approved AMIR NAZARIAN
Smoke Detectors 3/14/2024 Approved AMIR NAZARIAN
Final 3/22/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 3/22/2024 Approved AMIR NAZARIAN
Final 3/28/2024 OK to Issue CofO AMIR NAZARIAN