2031-2033 S CABRILLO AVE 90731
Certificate Information: 2031-2033 S CABRILLO AVE 90731
- Application / Permit
- 22014-30000-02404
- Plan Check / Job No.
- B22WL01987
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 140 SF PATIO COVER ADDITION AND 76 SF OPEN TRELLIS TO (E) SFD PER STD DETAIL.
- Permit Issued
- Issued on 1/10/2023
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 2/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2022 | ALFREDO JARA |
| Corrections Issued | 7/5/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 8/24/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 9/20/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 11/7/2022 | ALFREDO JARA |
| Plan Check Approved | 12/20/2022 | ALFREDO JARA |
| Building Plans Picked Up | 12/29/2022 | APPLICANT |
| Issued | 1/10/2023 | APPLICANT |
| CofO in Progress | 2/27/2023 | ANSON MAGLASANG |
| CofO Issued | 2/27/2023 | ANSON MAGLASANG |
| Permit Finaled | 2/27/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/25/2022 | ALFREDO JARA |
| Miscellaneous | Cleared | 9/9/2022 | DANIEL CORONADO |
| Miscellaneous | Cleared | 9/9/2022 | DANIEL CORONADO |
| Roof/Waste drainage to street | Cleared | 9/12/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2022 | JOSE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tiongco,, John Lazarraga; Lic. No.: C70915 | 17715 CANEHILL AVE BELLFLOWER, CA 90706 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/8/2023 | No Access for Inspection | JULIAN AMAYA |
| BUILDING-Rough-Frame | 2/10/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 2/10/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2023 | Approved | ANSON MAGLASANG |
| Wood Frame | 2/17/2023 | Conditional Approval | ANSON MAGLASANG |
| Final | 2/23/2023 | No Access for Inspection | JAMES CHAVEZ |
| Footing/Foundation/Slab | 2/23/2023 | No Access for Inspection | JAMES CHAVEZ |
| Green Building Final | 2/23/2023 | No Access for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 2/23/2023 | No Access for Inspection | JAMES CHAVEZ |
| Wood Frame | 2/23/2023 | No Access for Inspection | JAMES CHAVEZ |
| Final | 2/27/2023 | OK to Issue CofO | ANSON MAGLASANG |
| Footing/Foundation/Slab | 2/27/2023 | Approved | ANSON MAGLASANG |
| Green Building Final | 2/27/2023 | Approved | ANSON MAGLASANG |
| Smoke Detectors | 2/27/2023 | Approved | ANSON MAGLASANG |