2545-2547 S KELTON AVE 90064
Certificate Information: 2545-2547 S KELTON AVE 90064
- Application / Permit
- 22014-30000-02368
- Plan Check / Job No.
- B22WL01970
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- remodel of (e) 2,013 sf one story S.F.D. w/ attached garage. 451 sf 2-story addition to an existing 217 sf attacched garage, conversion to an ADU per Ordinance
- Permit Issued
- Issued on 10/23/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | KAVIAN REFAHI |
| Corrections Issued | 5/29/2022 | KAVIAN REFAHI |
| Quality Review Completed | 6/8/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 9/28/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 9/30/2022 | APPLICANT |
| Applicant returned to address corrections | 4/10/2023 | KAVIAN REFAHI |
| Plan Check Approved | 5/24/2023 | KAVIAN REFAHI |
| Issued | 10/23/2023 | APPLICANT |
| CofO in Progress | 11/21/2024 | DANIEL VERA |
| Permit Finaled | 12/3/2024 | RICHARD STEINBACH |
| CofO Issued | 12/3/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/3/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/28/2022 | KAVIAN REFAHI |
| Sewer availability | Cleared | 11/8/2022 | JENSON LEE |
| Address approval | Cleared | 11/21/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 11/21/2022 | JENSON LEE |
| Specific Plan | Cleared | 1/9/2023 | ROBERT SANCHEZ |
| GPI Written Notices | Cleared | 5/4/2023 | KAVIAN REFAHI |
Contact Information
| Architect | Ryan,, Oonagh C; Lic. No.: C33156 | 923 E 3RD STREET #105 LOS ANGELES, CA 90013 |
| Contractor | After Collaborative Inc; Lic. No.: 1077530-B | 3435 WILSHIRE BLVD SUITE 1400 LOS ANGELES, CA 90010 |
| Engineer | Mahlow,, Elizabeth Joy Johnson; Lic. No.: C80463 | 600 WILSHIRE BLVD SUITE 760 LOS ANGELES, CA 90065 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/12/2024 | Approved | JESUS PINEDA |
| Deputy Wood Construction | 1/31/2024 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2024 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Approved | MICHAEL PELHAM |
| Gas Test | 4/18/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 4/18/2024 | Approved | JESUS PINEDA |
| Sewer | 4/18/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 5/13/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 5/13/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 5/17/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 5/17/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/17/2024 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/21/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 5/21/2024 | Approved | JESUS PINEDA |
| Special/Order Compliance | 5/21/2024 | Corrections Issued | JESUS PINEDA |
| Insulation | 5/29/2024 | Corrections Issued | JESUS PINEDA |
| Insulation | 6/3/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 6/12/2024 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 6/12/2024 | Approved | KENNETH NAGLE |
| Shower Pan | 6/12/2024 | Approved | KENNETH NAGLE |
| Final | 10/21/2024 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 10/21/2024 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 10/21/2024 | Not Ready for Inspection | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Not Ready | DANIEL VERA |
| Smoke Detectors | 10/21/2024 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 11/4/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 11/4/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 11/4/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 11/4/2024 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 11/4/2024 | SGSOV Not Ready | TEMISTOCLES CAAL |
| Smoke Detectors | 11/4/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 11/7/2024 | OK to Issue CofO | DANIEL VERA |
| Green Building Final | 11/7/2024 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 11/7/2024 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 11/7/2024 | Approved | DANIEL VERA |