4120 N HAYVENHURST DR 91436

Certificate Information: 4120 N HAYVENHURST DR 91436

Application / Permit
22014-30000-02318
Plan Check / Job No.
B22WL01930
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and remodel (E) SFD. Per enigneering design.
Permit Issued
Issued on 10/3/2022
Issuing Office
Current Status
CofO Issued on 9/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2022 APPLICANT
Assigned to Plan Check Engineer 5/20/2022 RICHARD GARCIA
Corrections Issued 5/20/2022 RICHARD GARCIA
Applicant returned to address corrections 8/5/2022 RICHARD GARCIA
Applicant returned to address corrections 9/7/2022 ALFREDO JARA
Plan Check Approved 9/27/2022 ALFREDO JARA
Issued 10/3/2022 APPLICANT
Building Plans Picked Up 10/5/2022 APPLICANT
CofO in Progress 8/9/2023 VINCENT HANLEY
Permit Finaled 9/8/2023 JOHN JANSON
CofO Issued 9/8/2023 JOHN JANSON
Permit Finaled 9/8/2023 JOHN JANSON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/16/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/16/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/16/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/16/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/16/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/16/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 7/5/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 7/27/2022 CARLOS AGUILERA
Construction near power lines Cleared 8/18/2022 RIDWAN HARDY
Construction within easement Cleared 8/18/2022 RIDWAN HARDY

Contact Information

Contractor Advanced Building And Remodeling Inc; Lic. No.: 1064387-B 4470 W SUNSET BLVD 366      LOS ANGELES, CA 90027
Engineer Padilla,, Joseph G; Lic. No.: C72117 1553 PICASSO LN      OXNARD, CA 93033

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/5/2022 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 10/6/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 10/6/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/30/2022 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/30/2022 Partial Approval VINCENT HANLEY
Green Building Rough 12/30/2022 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 12/30/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 12/30/2022 Corrections Issued VINCENT HANLEY
Wood Frame 12/30/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 1/30/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/30/2023 Approved VINCENT HANLEY
Gas Test 1/30/2023 Partial Approval VINCENT HANLEY
Green Building Rough 1/30/2023 Not Ready for Inspection VINCENT HANLEY
Rough-Elec/Plmb/HVAC 1/30/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/3/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Approved VINCENT HANLEY
Green Building Rough 2/3/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/3/2023 Not Ready for Inspection VINCENT HANLEY
Shower Pan 2/3/2023 Approved VINCENT HANLEY
Insulation 2/8/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/8/2023 Partial Approval VINCENT HANLEY
Drywall Nailing 2/24/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 3/21/2023 Not Ready for Inspection VINCENT HANLEY
Interior/Exterior Lathing 4/28/2023 Partial Approval SEAN WIRCH
Final 7/6/2023 Corrections Issued VINCENT HANLEY
Green Building Final 7/6/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/6/2023 SGSOV Approved VINCENT HANLEY
Smoke Detectors 7/6/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 8/8/2023 Approved VINCENT HANLEY
Final 8/8/2023 OK to Issue CofO VINCENT HANLEY
PLUMBING-Final 8/8/2023 Approved VINCENT HANLEY