871 S WELLESLEY AVE 90049

Certificate Information: 871 S WELLESLEY AVE 90049

Application / Permit
22014-30000-02068
Plan Check / Job No.
B22WL01642
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) raised deck on piles attached to SFD *** 1 of 2 ***
Permit Issued
Issued on 6/14/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 KAVIAN REFAHI
Corrections Issued 5/16/2022 KAVIAN REFAHI
Quality Review Completed 5/25/2022 CHIHARU SUZUKI
Applicant returned to address corrections 10/23/2022 KAVIAN REFAHI
Applicant returned to address corrections 10/31/2022 KAVIAN REFAHI
Building Plans Picked Up 10/31/2022 APPLICANT
Applicant returned to address corrections 5/8/2024 KAVIAN REFAHI
Plan Check Approved 6/5/2024 KAVIAN REFAHI
Issued 6/14/2024 APPLICANT
CofO in Progress 12/9/2025 MICHAEL ALLEN
Permit Finaled 12/12/2025 RICHARD STEINBACH
CofO Issued 12/12/2025 RICHARD STEINBACH
Permit Finaled 12/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/18/2022 JENSON LEE
Watercourse Cleared 11/22/2022 HISASHI KOBAYAKAWA
Low Impact Development Cleared 2/28/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 4/25/2024 HISASHI KOBAYAKAWA

Contact Information

Contractor Farahi Construction Inc; Lic. No.: 584288-B 2933 BEVERLY GLEN CIRCLE      LOS ANGELES, CA 90077
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 3/26/2025 Conditional Approval KIRK SANDERS
Excavation/Setback/Form/Re-Bar 4/1/2025 Not Ready for Inspection KIRK SANDERS
Piling/Pier/Caisson 4/1/2025 Not Ready for Inspection KIRK SANDERS
Excavation/Setback/Form/Re-Bar 4/7/2025 Conditional Approval KIRK SANDERS
Piling/Pier/Caisson 4/7/2025 Conditional Approval KIRK SANDERS
Reinforced Concrete Frame 4/7/2025 Conditional Approval KIRK SANDERS
Special/Order Compliance 4/7/2025 Corrections Issued KIRK SANDERS
Deputy Reinf. Concrete 5/6/2025 Conditional Approval CARLOS MATAMOROS
Wood Frame 6/18/2025 Conditional Approval ARAM AVEDISIAN
Final 10/14/2025 Corrections Issued MICHAEL ALLEN
Footing/Foundation/Slab 10/14/2025 Approved MICHAEL ALLEN
Green Building Final 10/14/2025 Approved MICHAEL ALLEN
Green Building Rough 10/14/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 10/14/2025 Not Ready for Inspection MICHAEL ALLEN
Wood Frame 10/14/2025 Approved MICHAEL ALLEN
Final 11/5/2025 Conditional Approval MICHAEL ALLEN
Smoke Detectors 11/5/2025 Approved MICHAEL ALLEN
Final 11/25/2025 Corrections Issued DAVID FEILER
Final 12/4/2025 Conditional Approval MICHAEL ALLEN
Final 12/8/2025 OK to Issue CofO MICHAEL ALLEN