3159 S HADDINGTON DR 90064
Certificate Information: 3159 S HADDINGTON DR 90064
- Application / Permit
- 22014-30000-01850
- Plan Check / Job No.
- B22WL01539
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and addition to (E) S.F.D.
- Permit Issued
- Issued on 10/12/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2022 | JASON JANGADA |
| Corrections Issued | 4/22/2022 | JASON JANGADA |
| Building Plans Picked Up | 4/26/2022 | APPLICANT |
| Applicant returned to address corrections | 8/9/2022 | DANIEL SANJUAN |
| Plan Check Approved | 10/12/2022 | GEORGE ALVAREZ |
| Issued | 10/12/2022 | APPLICANT |
| CofO in Progress | 7/5/2024 | KIRK SANDERS |
| Permit Finaled | 7/31/2024 | DANIEL ORRANTE |
| CofO Issued | 7/31/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/31/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/31/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | DINAH GARIN |
| Low Impact Development | Cleared | 8/4/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 10/12/2022 | JASON JANGADA |
Contact Information
| Architect | Blumenberg,, Richard Leo; Lic. No.: C10862 | 15200 SUNSET BLVD STE 201 PACIFIC PALISADES, CA 90272 |
| Contractor | Nailed Construction Inc; Lic. No.: 821689-B | 448 SOUTH ROXBURY DRIVE BEVERLY HILLS, CA 90212 |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/24/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 2/1/2023 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 2/1/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Deputy Drilled-In Anchors | 2/2/2023 | No Access for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 2/3/2023 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2023 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 2/15/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| MERV13>=Rough | 2/15/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 2/21/2023 | No Access for Inspection | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Rough | 2/28/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| MERV13>=Rough | 2/28/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Underground Mechanical | 2/28/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 3/6/2023 | Partial Approval | ASHLEY THOMPSON |
| MERV13>=Rough | 3/6/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2023 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 4/21/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Rough | 5/3/2023 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 5/11/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 5/11/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 5/26/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Rough | 5/26/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| MERV13>=Rough | 5/26/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Insulation | 6/9/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 6/27/2023 | Corrections Issued | JEREMY TODD |
| BUILDING-Rough-Frame | 6/28/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Drywall Nailing | 6/28/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 6/28/2023 | Approved | CLAYTON GRAHAM |
| MERV13>=Rough | 6/28/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 6/30/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 6/30/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| MERV13>=Rough | 6/30/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 7/11/2023 | Partial Approval | CLAYTON GRAHAM |
| Shower Pan | 7/11/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 7/25/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 8/2/2023 | Partial Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/12/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 9/12/2023 | Approved | ARAM AVEDISIAN |
| MERV13>=Rough | 9/12/2023 | Approved | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 9/13/2023 | Conditional Approval | MICHAEL PELHAM |
| Masonry Wall/Backfill | 9/18/2023 | Partial Approval | CARLOS MATAMOROS |
| Masonry Wall/Backfill | 10/2/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 12/1/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Service/Power Release | 12/1/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 2/16/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Final | 3/5/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Final | 3/5/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 3/26/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 3/26/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 3/26/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 4/1/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 4/1/2024 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Final | 4/1/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/1/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/1/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 7/5/2024 | OK to Issue CofO | KIRK SANDERS |