1620 S POINT VIEW ST 90035

Certificate Information: 1620 S POINT VIEW ST 90035

Application / Permit
22014-30000-01741
Plan Check / Job No.
B22WL01451
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1st (829 sf) and 2nd (1,071 sf) floor addition to (e) 1-story SFD (1,401 sf)
Permit Issued
Issued on 3/6/2023
Issuing Office
West Los Angeles
Current Status
Issued on 3/6/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/13/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 REZA HAGHIGHAT
Corrections Issued 5/13/2022 REZA HAGHIGHAT
Quality Review Completed 5/18/2022 CHIHARU SUZUKI
Applicant returned to address corrections 10/11/2022 REZA HAGHIGHAT
Building Plans Picked Up 10/28/2022 APPLICANT
Applicant returned to address corrections 12/5/2022 REZA HAGHIGHAT
Plan Check Approved 12/15/2022 REZA HAGHIGHAT
Issued 3/6/2023 APPLICANT

Permit Application Clearance Information

Permit Cleared 7/5/2022 STEVE MELGAR
Low Impact Development Cleared 9/27/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 9/29/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/6/2022 STEVE MELGAR
Sewer availability Cleared 10/6/2022 STEVE MELGAR

Contact Information

Architect , ; Lic. No.: C34486 6151 CANTERBURY DRIVE   # 302    CULVER CITY, CA 90230
Contractor Gs Complete Builders Inc; Lic. No.: 1070465-B 9445 MELITA STREET      PICO RIVERA, CA 90660
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/19/2023 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 8/2/2023 Approved JOSE AVILA
Footing/Foundation/Slab 8/3/2023 Corrections Issued JOSE AVILA
METHANE-Barrier 8/3/2023 Approved JOSE AVILA
METHANE-Subgrade 8/3/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 8/28/2023 Partial Approval JOSE AVILA
PLUMBING-Rough 8/28/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 9/5/2023 No Access for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Conditional Approval JOSE AVILA
Deputy Wood Construction 9/11/2023 Approved LILIANA PORTILLO
Deputy Wood Construction 9/28/2023 Conditional Approval JOSE AVILA
Deputy Wood Construction 10/4/2023 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/6/2023 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 10/13/2023 Corrections Issued JOSE AVILA
Deputy Wood Construction 11/8/2023 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Partial Approval JOSE AVILA
Deputy Wood Construction 12/12/2023 Partial Approval SCOTT FINNILA
PLUMBING-Rough 12/27/2023 Approved JOAQUIN GREENOUGH
Deputy Wood Construction 1/11/2024 Conditional Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 1/11/2024 Corrections Issued SCOTT FINNILA
Shower Pan 1/11/2024 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Partial Approval STUART CHAPMAN
Shower Pan 1/17/2024 Approved STUART CHAPMAN
Underground Mechanical 1/17/2024 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 1/23/2024 Approved STUART CHAPMAN
ELECTRICAL-Rough 1/23/2024 Approved STUART CHAPMAN
Green Building Rough 1/23/2024 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 1/23/2024 Approved STUART CHAPMAN
Interior/Exterior Lathing 1/23/2024 Partial Approval STUART CHAPMAN
METHANE-Rough 1/23/2024 Approved STUART CHAPMAN
Insulation 1/31/2024 Approved RICHARD DOCKUS
Interior/Exterior Lathing 1/31/2024 Partial Approval RICHARD DOCKUS
Drywall Nailing 2/14/2024 Approved STUART CHAPMAN
Green Building Rough 2/14/2024 Approved STUART CHAPMAN
Interior/Exterior Lathing 2/26/2024 Approved STUART CHAPMAN
Gas Test 4/11/2024 Partial Approval RICHARD DOCKUS
Sewer 4/11/2024 Approved RICHARD DOCKUS
ELECTRICAL-Final 10/4/2024 Approved ARTHUR NEGRETE
HVAC-Final 10/22/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 10/22/2024 Approved ARTHUR NEGRETE
Underground Mechanical 10/22/2024 Approved ARTHUR NEGRETE
Final 12/10/2024 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 12/10/2024 Approved ENRIQUE MIRELES
Green Building Final 12/10/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/10/2024 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/10/2024 Approved ENRIQUE MIRELES
Final 2/14/2025 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Final 2/27/2025 Approved ARTHUR NEGRETE
Service/Power Release 2/27/2025 Approved ARTHUR NEGRETE