11616 1/2-1/3 W HAMLIN ST 91606

Certificate Information: 11616 1/2-1/3 W HAMLIN ST 91606

Application / Permit
22014-30000-01619
Plan Check / Job No.
B22WL01382
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 2-story duplex at front of the lot
Permit Issued
Issued on 12/14/2023
Issuing Office
Metro
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 TARIK SAOUD
Corrections Issued 8/29/2022 TARIK SAOUD
Quality Review Completed 9/6/2022 CHIHARU SUZUKI
Building Plans Picked Up 9/13/2022 APPLICANT
Disabled Access Plans Picked Up 3/22/2023 APPLICANT
Green Plans Picked Up 10/4/2023 APPLICANT
Applicant returned to address corrections 12/4/2023 REZA HAGHIGHAT
Plan Check Approved 12/8/2023 REZA HAGHIGHAT
Issued 12/14/2023 APPLICANT
CofO in Progress 1/8/2026 ROBERTO PALACIOS-LOPEZ
Permit Finaled 1/28/2026 RUBEN SALAS
CofO Issued 1/28/2026 RUBEN SALAS
Permit Finaled 1/28/2026 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/31/2022 KURT CORRAL
Address approval Cleared 12/28/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/3/2023 CARLOS AGUILERA
Sewer availability Cleared 1/3/2023 CARLOS AGUILERA
Frnt yard landscape/Water mgmt Cleared 4/19/2023 DANIEL CORONADO
Low Impact Development Cleared 8/11/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 8/15/2023 CARLOS AGUILERA
DAS Clearance Cleared 8/23/2023 SHINE LIN
Green Code Cleared 10/10/2023 MICHAEL AYERS

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Architect Mcvay,, Bruce Cameron; Lic. No.: C11870 6440 E. EL ROBLE STREET      LONG BEACH, CA 90815
Contractor Quakestrong; Lic. No.: 1037437-B 1213 LA BREA AVENUE      LOS ANGELES, CA 90019

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/23/2024 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/23/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 10/28/2024 Not Ready for Inspection KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 11/5/2024 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 11/5/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 11/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 11/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 11/19/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Wood Frame 12/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 1/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Sewer 1/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 1/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 1/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 1/24/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 1/24/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 1/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 1/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 1/30/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 1/30/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/5/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/5/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/5/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/5/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 2/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 2/5/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Drywall Nailing 2/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 2/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Sewer 3/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Gas Test 4/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 6/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 6/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 6/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 6/16/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 6/16/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Gas Test 6/20/2025 Partial Approval DAVID ANDERSON
Final 8/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 8/13/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 8/13/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 8/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 8/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 10/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 10/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 12/31/2025 Corrections Issued JOSE AVILA
Final 1/6/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 1/6/2026 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/6/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 1/8/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/8/2026 Approved ROBERTO PALACIOS-LOPEZ