400 S SALTAIR AVE 90049
Certificate Information: 400 S SALTAIR AVE 90049
- Application / Permit
- 22014-30000-01513
- Plan Check / Job No.
- B22WL01288
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- Addition to ALQ
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2022 | KAVIAN REFAHI |
| Corrections Issued | 4/10/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 4/14/2022 | APPLICANT |
| Applicant returned to address corrections | 10/11/2022 | DANIEL SANJUAN |
| Plan Check Approved | 10/27/2022 | DANIEL SANJUAN |
| Issued | 10/27/2022 | APPLICANT |
| CofO in Progress | 6/28/2023 | OGANES TARAKHCHYAN |
| Permit Finaled | 1/8/2024 | DANIEL ORRANTE |
| CofO Issued | 1/8/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/8/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 7/13/2022 | RUBEN VASQUEZ |
| Low Impact Development | Cleared | 7/28/2022 | JULIAN SUNG |
| Grading Pre-Inspection | Cleared | 10/11/2022 | KAVIAN REFAHI |
| Address approval | Cleared | 10/17/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2022 | JENSON LEE |
| Sewer availability | Cleared | 10/18/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 10/25/2022 | JEANIE LAM |
| GPI Written Notices | Cleared | 10/27/2022 | KAVIAN REFAHI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nagra,, Sukhdeep Singh; Lic. No.: C84908 | PO BOX 1836 YUBA CITY, CA 95992 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/28/2022 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/10/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 11/16/2022 | Approved | RICHARD STEINBACH |
| Wood Frame | 12/1/2022 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2022 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | ASHLEY THOMPSON |
| FLOOD-Proofing Certificate | 1/13/2023 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 1/13/2023 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 1/13/2023 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 1/18/2023 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/20/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 1/20/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 1/26/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 2/6/2023 | Approved | CARLOS MATAMOROS |
| Final | 6/12/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 6/12/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 6/12/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 6/27/2023 | OK to Issue CofO | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Approved | OGANES TARAKHCHYAN |