212 N ADERNO WAY 90272
Certificate Information: 212 N ADERNO WAY 90272
- Application / Permit
- 22014-30000-01477
- Plan Check / Job No.
- B22WL01257
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and Ground Floor Addition to (E) 1-Story S.F.D w/Attached Garage
- Permit Issued
- Issued on 8/24/2022
- Issuing Office
- Current Status
- CofO Issued on 7/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | DAVID CASTILLO |
| Corrections Issued | 4/26/2022 | DAVID CASTILLO |
| Quality Review Completed | 5/2/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 5/2/2022 | APPLICANT |
| Applicant returned to address corrections | 7/28/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 8/3/2022 | DAVID CASTILLO |
| Plan Check Approved | 8/19/2022 | DAVID CASTILLO |
| Issued | 8/24/2022 | APPLICANT |
| CofO in Progress | 7/25/2023 | GERMAN RODRIGUEZ MENDOZA |
| Permit Finaled | 7/26/2023 | DANIEL ORRANTE |
| CofO Issued | 7/26/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/26/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/10/2022 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 5/10/2022 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 5/10/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2022 | CATHERINE ADROVER |
| Permit | Cleared | 5/11/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 5/11/2022 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 6/16/2022 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 6/16/2022 | RAYMOND MUGAMBWA |
| Trees in Parkway | Cleared | 6/22/2022 | ADALBERTO VERA |
| Coastal Zone | Cleared | 7/5/2022 | DALIA MOKAYED |
| ZI | Cleared | 7/5/2022 | DALIA MOKAYED |
| Low Impact Development | Cleared | 7/18/2022 | ORVAL HERNANDEZ-MARCI |
| Grading Pre-Inspection | Cleared | 8/3/2022 | DAVID CASTILLO |
| Roof/Waste drainage to street | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| Hold | Cleared | 9/27/2022 | JEREMY CORONEL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Clemons,, Patrick Henry; Lic. No.: L7513 | 1843 SUMMER CLOUD DR THOUSAND OAKS, CA 91363 |
| Engineer | Judd,, Shane Dennis; Lic. No.: C70991 | 17 E HIGH ST STE A MOORPARK, CA 93021 |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 3101 OCEAN PARK BLVD STE 100, PMB 122 SANTA MONICA, CA 90405 |
| Geologist | Barrett,, Mark A; Lic. No.: EG2088 | 14428 HAMLIN ST 200 VAN NUYS, CA 91401 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/30/2022 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 10/12/2022 | Not Ready for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 10/12/2022 | Not Ready for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 10/14/2022 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 10/14/2022 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 10/17/2022 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/20/2022 | Partial Approval | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 10/25/2022 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/1/2022 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 11/1/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 11/1/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 11/1/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 11/3/2022 | Partial Approval | BRENDAN LOONEY |
| Wood Frame | 11/30/2022 | Conditional Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 12/19/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| ELECTRICAL-Rough | 12/19/2022 | Corrections Issued | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Corrections Issued | MICHAEL PELHAM |
| Green Building Rough | 12/19/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| HVAC-Rough | 12/19/2022 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 12/19/2022 | Corrections Issued | MICHAEL PELHAM |
| Verify Sprinkler Sign Off | 12/19/2022 | Corrections Issued | MICHAEL PELHAM |
| Deputy Wood Construction | 12/20/2022 | Conditional Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 12/28/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 12/28/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 12/28/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 12/28/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 12/28/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 1/6/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 1/6/2023 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Special/Order Compliance | 1/10/2023 | Partial Inspection | MICHAEL PELHAM |
| Wood Frame | 1/10/2023 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 1/11/2023 | Corrections Issued | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 1/25/2023 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 1/25/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 1/27/2023 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 1/27/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Rough-Elec/Plmb/HVAC | 1/30/2023 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 2/3/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 2/3/2023 | Approved | BRENDAN LOONEY |
| Wood Frame | 2/9/2023 | Partial Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 2/23/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Shower Pan | 2/23/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/27/2023 | Not Ready for Inspection | KENNETH NAGLE |
| Shower Pan | 2/27/2023 | Not Ready for Inspection | KENNETH NAGLE |
| Wood Frame | 2/27/2023 | Not Ready for Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 2/28/2023 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 2/28/2023 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 2/28/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Shower Pan | 2/28/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 3/3/2023 | Partial Approval | BRENDAN LOONEY |
| Shower Pan | 3/3/2023 | Corrections Issued | BRENDAN LOONEY |
| Insulation | 3/13/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Insulation | 3/14/2023 | Conditional Approval | BRENDAN LOONEY |
| Drywall Nailing | 3/20/2023 | Conditional Approval | BRENDAN LOONEY |
| Shower Pan | 3/28/2023 | Not Ready for Inspection | JESUS PINEDA |
| Shower Pan | 3/30/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/31/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 5/31/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 6/6/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 6/27/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 6/27/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 6/27/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 6/27/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 7/6/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 7/6/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 7/6/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 7/6/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 7/6/2023 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 7/6/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 7/10/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 7/10/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 7/10/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 7/12/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Final | 7/20/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |