835 E PALMS BLVD 90291
Certificate Information: 835 E PALMS BLVD 90291
- Application / Permit
- 22014-30000-01460
- Plan Check / Job No.
- B22WL01249
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Attach new laundry room to garage. Design per engineer's calcs.
- Permit Issued
- Issued on 11/14/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | ALFREDO JARA |
| Corrections Issued | 5/12/2024 | ALFREDO JARA |
| Corrections Issued | 5/13/2024 | REZA HAGHIGHAT |
| Building Plans Picked Up | 5/20/2024 | APPLICANT |
| Plan Check Approved | 11/14/2024 | CAROLEAN BASMA |
| Issued | 11/14/2024 | APPLICANT |
| CofO in Progress | 6/27/2025 | JESUS RODRIGUEZ |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
| CofO Issued | 7/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2024 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 9/11/2024 | VLADIMIR ARUTYUNYAN |
| Coastal Zone | Cleared | 9/12/2024 | ROSALINDA MEZA |
| Specific Plan | Cleared | 11/4/2024 | LUIS LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Final | 1/27/2025 | Not Ready for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 1/27/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 1/27/2025 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/29/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/29/2025 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/29/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 5/29/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 5/29/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/29/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/29/2025 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 6/4/2025 | Approved | JAYLIN GRAVITTE |
| Insulation | 6/4/2025 | Approved | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 6/13/2025 | Approved | MICHAEL ALLEN |
| Final | 6/13/2025 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 6/13/2025 | Approved | MICHAEL ALLEN |
| HVAC-Final | 6/13/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 6/13/2025 | Approved | MICHAEL ALLEN |
| Smoke Detectors | 6/13/2025 | Approved | MICHAEL ALLEN |
| Final | 6/26/2025 | OK to Issue CofO | JESUS RODRIGUEZ |