3657-3659 S BARRY AVE 90066
Certificate Information: 3657-3659 S BARRY AVE 90066
- Application / Permit
- 22014-30000-01410
- Plan Check / Job No.
- B22WL01207
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition (2760 sf) to (e) single story SFD (710 sf), add an attached 2-car garage (386 sf) and attached ADU (434 sf) per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 5/20/2022
- Issuing Office
- Current Status
- CofO Issued on 8/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | REZA HAGHIGHAT |
| Corrections Issued | 4/9/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 4/12/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 5/19/2022 | REZA HAGHIGHAT |
| Issued | 5/20/2022 | APPLICANT |
| Building Plans Picked Up | 5/23/2022 | APPLICANT |
| CofO in Progress | 8/17/2023 | JESUS PINEDA |
| Permit Finaled | 8/22/2023 | DANIEL ORRANTE |
| CofO Issued | 8/22/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/22/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2022 | STEVEN JIN |
| Permit | Cleared | 4/16/2022 | STEVEN JIN |
| Sewer availability | Cleared | 4/16/2022 | STEVEN JIN |
| Specific Plan | Cleared | 4/27/2022 | VALERIA CEJA |
| Low Impact Development | Cleared | 4/28/2022 | CHRIS VONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2022 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 4/30/2022 | JOSE HERNANDEZ |
| Trees in Parkway | Cleared | 5/13/2022 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 5/19/2022 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 5/19/2022 | REZA HAGHIGHAT |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/31/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 9/29/2022 | Conditional Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 9/30/2022 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 9/30/2022 | Corrections Issued | JOHNNY MIRANDA |
| Underground Mechanical | 9/30/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 10/4/2022 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 10/4/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 11/17/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 12/2/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 12/9/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 12/9/2022 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 2/2/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 2/17/2023 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 2/17/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Shower Pan | 2/22/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 2/27/2023 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/1/2023 | Corrections Issued | CLAYTON GRAHAM |
| Shower Pan | 3/1/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 3/10/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 3/10/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/10/2023 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 3/16/2023 | Corrections Issued | CLAYTON GRAHAM |
| Insulation | 3/21/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/30/2023 | Partial Approval | JOHNNY MIRANDA |
| Shower Pan | 3/30/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Drywall Nailing | 4/6/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Shower Pan | 4/6/2023 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 4/12/2023 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 4/12/2023 | Approved | RICHARD STEINBACH |
| Gas Test | 5/26/2023 | Corrections Issued | JOHNNY MIRANDA |
| Gas Test | 6/30/2023 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 7/27/2023 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 7/27/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 7/27/2023 | Corrections Issued | JESUS PINEDA |
| Service/Power Release | 7/27/2023 | Not Ready for Inspection | JESUS PINEDA |
| Sewer | 7/27/2023 | Corrections Issued | JESUS PINEDA |
| Verify Rec and Parks Fee Memo | 7/27/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 8/2/2023 | Approved | JESUS PINEDA |
| PLUMBING-Final | 8/2/2023 | Approved | JESUS PINEDA |
| Service/Power Release | 8/2/2023 | Approved | JESUS PINEDA |
| HVAC-Final | 8/9/2023 | Approved | JESUS PINEDA |
| Final | 8/11/2023 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 8/11/2023 | Approved | JESUS PINEDA |
| Green Building Final | 8/11/2023 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 8/11/2023 | Approved | JESUS PINEDA |
| Final | 8/17/2023 | OK to Issue CofO | JESUS PINEDA |