1608 1/2 W 52ND ST 90062
Certificate Information: 1608 1/2 W 52ND ST 90062
- Application / Permit
- 22014-30000-01357
- Plan Check / Job No.
- B22WL01161
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition and conversion of (E) garage into an ADU per GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)¹, (d)¹, and (g) and WFPP
- Permit Issued
- Issued on 9/1/2022
- Issuing Office
- Current Status
- CofO Issued on 6/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | JASON JANGADA |
| Corrections Issued | 3/26/2022 | JASON JANGADA |
| Plan Check Approved | 9/1/2022 | KHUONG TRUONG |
| Issued | 9/1/2022 | APPLICANT |
| CofO in Progress | 6/11/2024 | DAVID FEILER |
| Permit Finaled | 6/11/2024 | DEROLD HAUFF |
| CofO Issued | 6/11/2024 | DEROLD HAUFF |
| Permit Finaled | 6/11/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 4/5/2022 | JEANETTE VONG |
| Community Plan Implem. Overlay | Cleared | 4/14/2022 | RAFAEL FONTES |
| Construction near power lines | Cleared | 8/23/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Divine Grace Construction; Lic. No.: 933197-B | 9672 ALONDRA BLVD BELLFLOWER, CA 90706 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/22/2023 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 9/22/2023 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 9/28/2023 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 11/7/2023 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 11/7/2023 | Partial Approval | CRAIG DAVIS |
| Green Building Rough | 11/7/2023 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Rough | 11/7/2023 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 11/7/2023 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 11/17/2023 | Approved | CRAIG DAVIS |
| HVAC-Rough | 11/17/2023 | Approved | CRAIG DAVIS |
| PLUMBING-Rough | 11/17/2023 | Partial Approval | CRAIG DAVIS |
| BUILDING-Rough-Frame | 11/28/2023 | Approved | RONNIE MINDANAO |
| Green Building Rough | 11/28/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/30/2023 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2023 | Partial Approval | CRAIG DAVIS |
| Drywall Nailing | 12/7/2023 | Approved | CRAIG DAVIS |
| Shower Pan | 12/7/2023 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/22/2024 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 2/22/2024 | Corrections Issued | DAVID FEILER |
| Final | 2/22/2024 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 2/22/2024 | Approved | DAVID FEILER |
| Green Building Final | 2/22/2024 | Corrections Issued | DAVID FEILER |
| Green Building Rough | 2/22/2024 | Approved | DAVID FEILER |
| HVAC-Final | 2/22/2024 | Corrections Issued | DAVID FEILER |
| PLUMBING-Final | 2/22/2024 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 2/22/2024 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 2/22/2024 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 4/11/2024 | Corrections Issued | JOSE MACIAS |
| Final | 4/11/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 4/11/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Final | 4/11/2024 | Approved | JOSE MACIAS |
| PLUMBING-Final | 4/11/2024 | Partial Approval | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 4/11/2024 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 4/11/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Final | 6/10/2024 | Approved | DAVID FEILER |
| Final | 6/10/2024 | OK to Issue CofO | DAVID FEILER |
| Green Building Final | 6/10/2024 | Approved | DAVID FEILER |
| HVAC-Final | 6/10/2024 | Approved | DAVID FEILER |
| PLUMBING-Final | 6/10/2024 | Approved | DAVID FEILER |
| Smoke Detectors | 6/10/2024 | Approved | DAVID FEILER |