4226 N COLBATH AVE 91423

Certificate Information: 4226 N COLBATH AVE 91423

Application / Permit
22014-30000-01296
Plan Check / Job No.
B22WL01106
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major Remodel, (N) Attached Garage, and 2-Story Addition to an (E) 1-Story S.F.D
Permit Issued
Issued on 7/13/2022
Issuing Office
Current Status
CofO Issued on 7/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 DAVID CASTILLO
Corrections Issued 4/7/2022 DAVID CASTILLO
Quality Review Completed 4/18/2022 CHIHARU SUZUKI
Building Plans Picked Up 4/22/2022 APPLICANT
Plan Check Approved 6/22/2022 DAVID CASTILLO
Issued 7/13/2022 APPLICANT
CofO in Progress 7/18/2023 MISAEL ESPARZA
Permit Finaled 7/19/2023 MICHAEL SMITH
CofO Issued 7/19/2023 MICHAEL SMITH
Permit Finaled 7/19/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/19/2022 DAGOVERTO GUERRERO
Permit Cleared 4/19/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 4/19/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 4/29/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 5/2/2022 DAGOVERTO GUERRERO
Trees in Parkway Cleared 5/6/2022 ADALBERTO VERA
Grading Pre-Inspection Cleared 6/21/2022 DAVID CASTILLO

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Nguyen,, Huan; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003
Engineer Toedter,, Randy Wayne; Lic. No.: C37316 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/18/2022 Partial Approval MISAEL ESPARZA
Pre-Inspection 8/25/2022 Approved MISAEL ESPARZA
Pre-Inspection 8/30/2022 Approved MISAEL ESPARZA
Deputy Reinf. Concrete 9/8/2022 Conditional Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 9/8/2022 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 9/12/2022 No Access for Inspection MISAEL ESPARZA
Deputy Reinf. Concrete 9/13/2022 Conditional Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 10/3/2022 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 10/5/2022 Approved MISAEL ESPARZA
Pre-Inspection 10/17/2022 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 12/13/2022 Approved MICHEL ABAJAN
Shower Pan 12/13/2022 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 12/14/2022 Corrections Issued MISAEL ESPARZA
Shower Pan 12/14/2022 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 12/15/2022 Approved MISAEL ESPARZA
HVAC-Rough 12/15/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 1/10/2023 No Access for Inspection MISAEL ESPARZA
Green Building Rough 1/10/2023 No Access for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 1/13/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 1/13/2023 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 1/24/2023 Conditional Approval MISAEL ESPARZA
Green Building Rough 1/24/2023 Not Ready for Inspection MISAEL ESPARZA
Underground Mechanical 1/26/2023 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 1/31/2023 Partial Approval MISAEL ESPARZA
Insulation 2/6/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 2/23/2023 Approved MISAEL ESPARZA
Sewer 2/23/2023 Corrections Issued MISAEL ESPARZA
Shower Pan 2/23/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/1/2023 Approved MISAEL ESPARZA
Drywall Nailing 3/28/2023 Approved MISAEL ESPARZA
Green Building Rough 3/28/2023 Approved MISAEL ESPARZA
Sewer 4/19/2023 Approved MATTHEW NELSON
ELECTRICAL-Rough 5/22/2023 Partial Inspection THOMAS FINNILA
ELECTRICAL-Final 6/14/2023 Partial Inspection JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 6/14/2023 Corrections Issued JOHN COLEMAN
HVAC-Final 6/14/2023 Approved JOHN COLEMAN
PLUMBING-Final 6/14/2023 Not Ready for Inspection JOHN COLEMAN
Service/Power Release 6/14/2023 Partial Inspection JOHN COLEMAN
BUILDING-Rough-Frame 6/21/2023 Approved JOHN COLEMAN
ELECTRICAL-Final 6/21/2023 Approved JOHN COLEMAN
Final 6/21/2023 Corrections Issued JOHN COLEMAN
Gas Test 6/21/2023 Approved JOHN COLEMAN
Green Building Final 6/21/2023 Approved JOHN COLEMAN
PLUMBING-Final 6/21/2023 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 6/21/2023 SGSOV Not Required JOHN COLEMAN
Smoke Detectors 6/21/2023 Approved JOHN COLEMAN
Final 7/17/2023 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 7/17/2023 Approved MISAEL ESPARZA