Interior Remodel and Addition to (E) S.F.D per Engineer's Calcs
Permit Issued
Issued on 6/10/2022
Issuing Office
Current Status
CofO Issued on 2/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 KAVIAN REFAHI
Corrections Issued 3/27/2022 KAVIAN REFAHI
Applicant returned to address corrections 5/10/2022 DAVID CASTILLO
Plan Check Approved 6/4/2022 DAVID CASTILLO
Building Plans Picked Up 6/6/2022 APPLICANT
Issued 6/10/2022 APPLICANT
CofO in Progress 1/27/2024 STUART CHAPMAN
Permit Finaled 2/19/2024 DEROLD HAUFF
CofO Issued 2/19/2024 DEROLD HAUFF
Permit Finaled 2/19/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/2/2022 CINDY QI
Roof/Waste drainage to street Cleared 5/2/2022 CINDY QI

Contact Information

Architect Asamoah,, B Kwesi; Lic. No.: C36558 850 ROSE AVENUE      VENICE, CA 90291
Contractor Freemodel Inc; Lic. No.: 1066986-B 141 CLARENDON ROAD      BURLINGAME, CA 94010

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/19/2022 Approved JOSE AVILA
METHANE-Barrier 7/19/2022 Approved JOSE AVILA
METHANE-Subgrade 7/19/2022 Approved JOSE AVILA
ELECTRICAL-Rough 11/4/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Partial Approval JOSE AVILA
Green Building Rough 11/4/2022 Corrections Issued JOSE AVILA
METHANE-Rough 11/4/2022 Approved JOSE AVILA
PLUMBING-Rough 11/4/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 11/23/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 11/23/2022 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 12/1/2022 Conditional Approval JOSE AVILA
PLUMBING-Rough 12/1/2022 Approved JOSE AVILA
Insulation 12/6/2022 Approved JOSE AVILA
Drywall Nailing 12/12/2022 Approved JOSE AVILA
Interior/Exterior Lathing 12/12/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 8/22/2023 Approved JOSE AVILA
Green Building Final 8/22/2023 Approved JOSE AVILA
Green Building Rough 8/22/2023 Approved JOSE AVILA
Smoke Detectors 8/22/2023 Corrections Issued JOSE AVILA
Final 1/10/2024 Corrections Issued RONNIE MINDANAO
Smoke Detectors 1/10/2024 Approved RONNIE MINDANAO
ELECTRICAL-Final 1/26/2024 Approved STUART CHAPMAN
Final 1/26/2024 OK to Issue CofO STUART CHAPMAN
HVAC-Final 1/26/2024 Approved STUART CHAPMAN
PLUMBING-Final 1/26/2024 Approved STUART CHAPMAN