1655 N AMALFI DR 90272
Certificate Information: 1655 N AMALFI DR 90272
- Application / Permit
- 22014-30000-01277
- Plan Check / Job No.
- B22WL01085
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- FIRST FLOOR ADDITION TO AN EXISTING 2-STORY SFD WITH ATTACHED GARAGE
- Permit Issued
- Issued on 6/24/2022
- Issuing Office
- Current Status
- CofO Issued on 3/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | TARIK SAOUD |
| Corrections Issued | 4/5/2022 | TARIK SAOUD |
| Quality Review Completed | 4/13/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 5/4/2022 | TARIK SAOUD |
| Issued | 6/24/2022 | APPLICANT |
| Building Plans Picked Up | 7/1/2022 | APPLICANT |
| CofO in Progress | 3/16/2023 | KEVIN SARGSYAN |
| Permit Finaled | 3/21/2023 | DANIEL ORRANTE |
| CofO Issued | 3/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/22/2022 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 4/22/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2022 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 5/4/2022 | TARIK SAOUD |
| Sewer availability | Cleared | 5/4/2022 | SAUL GARCIA |
Contact Information
| Architect | Pisani,, Tanya Chan; Lic. No.: C31357 | 11935 BEATRICE STREET LOS ANGELES, CA 90230 |
| Contractor | M V C Management; Lic. No.: 993381-B | 331 MANHATTAN AVE HERMOSA BEACH, CA 90254 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/22/2022 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/22/2022 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Corrections Issued | JUAN VALENZUELA |
| Insulation | 11/10/2022 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/28/2022 | Partial Approval | KENNETH NAGLE |
| ELECTRICAL-Rough | 11/28/2022 | Approved | KENNETH NAGLE |
| Green Building Rough | 11/28/2022 | Not Ready for Inspection | KENNETH NAGLE |
| HVAC-Rough | 11/28/2022 | Approved | KENNETH NAGLE |
| PLUMBING-Rough | 11/28/2022 | Approved | KENNETH NAGLE |
| Deputy Wood Construction | 11/29/2022 | Conditional Approval | JUAN VALENZUELA |
| Insulation | 11/30/2022 | Corrections Issued | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/5/2022 | Approved | KENNETH NAGLE |
| Green Building Rough | 12/5/2022 | Approved | KENNETH NAGLE |
| Insulation | 12/5/2022 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 12/5/2022 | Partial Approval | KENNETH NAGLE |
| Drywall Nailing | 12/8/2022 | Approved | DAVID FEILER |
| Shower Pan | 12/8/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 12/12/2022 | Approved | CLAYTON GRAHAM |
| Special/Order Compliance | 12/12/2022 | Partial Inspection | STEPHANIE SWANSON |
| Final | 3/7/2023 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 3/7/2023 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 3/7/2023 | Approved | KEVIN SARGSYAN |
| Final | 3/15/2023 | OK to Issue CofO | KEVIN SARGSYAN |
| Green Building Final | 3/15/2023 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/15/2023 | SGSOV Approved | KEVIN SARGSYAN |