2634 S VETERAN AVE 90064

Certificate Information: 2634 S VETERAN AVE 90064

Application / Permit
22014-30000-01243
Plan Check / Job No.
B22WL01034
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story house addition, removing entire S.F.D. w/ the exception of portion of wall & fdn.
Permit Issued
Issued on 6/10/2022
Issuing Office
Current Status
CofO Issued on 12/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 TARIK SAOUD
Corrections Issued 3/31/2022 TARIK SAOUD
Quality Review Completed 4/6/2022 CHIHARU SUZUKI
Plan Check Approved 6/2/2022 TARIK SAOUD
Building Plans Picked Up 6/2/2022 APPLICANT
Issued 6/10/2022 APPLICANT
CofO in Progress 6/13/2023 DAVID FEILER
Permit Finaled 12/30/2023 DANIEL ORRANTE
CofO Issued 12/30/2023 DANIEL ORRANTE
Permit Finaled 12/30/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/11/2022 HISASHI KOBAYAKAWA
Permit Cleared 4/11/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 4/11/2022 HISASHI KOBAYAKAWA
Specific Plan Cleared 4/12/2022 EDUARDO HERMOSO
Trees in Parkway Cleared 4/28/2022 ADALBERTO VERA
Low Impact Development Cleared 5/4/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/10/2022 DINAH GARIN
Grading Pre-Inspection Cleared 6/2/2022 TARIK SAOUD

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Wassef,, Mena; Lic. No.: C84979 28131 VALERIO CT      VALENCIA, CA 91354

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/19/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 7/22/2022 Partial Approval EVAN COOPER
Footing/Foundation/Slab 8/8/2022 Corrections Issued JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 8/9/2022 Approved JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 8/11/2022 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 10/11/2022 Not Ready for Inspection MICHAEL PELHAM
ELECTRICAL-Rough 10/11/2022 Corrections Issued MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Corrections Issued MICHAEL PELHAM
Green Building Rough 10/11/2022 Not Ready for Inspection MICHAEL PELHAM
HVAC-Rough 10/11/2022 Corrections Issued MICHAEL PELHAM
PLUMBING-Rough 10/11/2022 Not Ready for Inspection MICHAEL PELHAM
ELECTRICAL-Rough 10/27/2022 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Partial Approval JOHNNY MIRANDA
Green Building Rough 10/27/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 10/27/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 10/27/2022 Corrections Issued JOHNNY MIRANDA
Wood Frame 10/27/2022 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 10/31/2022 Approved JOHNNY MIRANDA
HVAC-Rough 10/31/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 10/31/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 10/31/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 11/7/2022 Approved STEPHANIE SWANSON
Green Building Rough 11/7/2022 Approved STEPHANIE SWANSON
Insulation 11/7/2022 Corrections Issued STEPHANIE SWANSON
Shower Pan 11/7/2022 Corrections Issued STEPHANIE SWANSON
Insulation 11/14/2022 Approved STEPHANIE SWANSON
Drywall Nailing 11/17/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 12/7/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 3/7/2023 Not Ready for Inspection JOHNNY MIRANDA
Final 3/7/2023 Not Ready for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 3/7/2023 Approved JOHNNY MIRANDA
Green Building Final 3/7/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Final 3/7/2023 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Final 3/7/2023 Not Ready for Inspection JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Not Ready JOHNNY MIRANDA
Service/Power Release 3/7/2023 Not Ready for Inspection JOHNNY MIRANDA
Smoke Detectors 3/7/2023 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Final 3/28/2023 Approved JOHNNY MIRANDA
Final 3/28/2023 Corrections Issued JOHNNY MIRANDA
Green Building Final 3/28/2023 Approved JOHNNY MIRANDA
HVAC-Final 3/28/2023 Approved JOHNNY MIRANDA
PLUMBING-Final 3/28/2023 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 3/28/2023 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 3/28/2023 Approved JOHNNY MIRANDA
Final 4/4/2023 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Final 4/4/2023 Not Ready for Inspection JOHNNY MIRANDA
Final 4/20/2023 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 4/20/2023 Approved JOHNNY MIRANDA
Final 6/13/2023 OK to Issue CofO DAVID FEILER
Service/Power Release 6/13/2023 Approved DAVID FEILER