1035 E VERNON AVE 90291
Certificate Information: 1035 E VERNON AVE 90291
- Application / Permit
- 22014-30000-01196
- Plan Check / Job No.
- B22WL01004
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION & INTERIOR REMODEL KITCHEN TO (E) SFD
- Permit Issued
- Issued on 7/3/2022
- Issuing Office
- Current Status
- CofO Issued on 5/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | RICHARD GARCIA |
| Corrections Issued | 3/19/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 6/6/2022 | RICHARD GARCIA |
| Plan Check Approved | 6/22/2022 | FERNANDO FLORES |
| Issued | 7/3/2022 | APPLICANT |
| Building Plans Picked Up | 7/5/2022 | APPLICANT |
| CofO in Progress | 5/24/2023 | HERBERT GIRON |
| Permit Finaled | 5/31/2023 | DANIEL ORRANTE |
| CofO Issued | 5/31/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/31/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/2/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2022 | SAUL GARCIA |
| Specific Plan | Cleared | 5/12/2022 | COLLINS ALLAN |
| Roof/Waste drainage to street | Cleared | 6/8/2022 | SAUL GARCIA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/5/2022 | Partial Inspection | STEPHANIE SWANSON |
| Pre-Inspection | 8/9/2022 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 8/16/2022 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 8/30/2022 | Partial Approval | CLAYTON GRAHAM |
| Green Building Rough | 8/30/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 8/30/2022 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Wood Construction | 10/7/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Wood Construction | 10/12/2022 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 11/4/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 11/4/2022 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2022 | Not Ready for Inspection | DAVID FEILER |
| Gas Test | 11/4/2022 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 11/4/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 11/4/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 11/4/2022 | Not Ready for Inspection | DAVID FEILER |
| Deputy Other (see comments) | 11/9/2022 | No Access for Inspection | CLAYTON GRAHAM |
| Deputy Wood Construction | 11/9/2022 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 11/15/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 11/15/2022 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Partial Approval | DAVID FEILER |
| Gas Test | 11/15/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 11/15/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 11/15/2022 | Approved | DAVID FEILER |
| PLUMBING-Rough | 11/15/2022 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 12/16/2022 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 12/16/2022 | Approved | EVAN COOPER |
| Green Building Rough | 12/16/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 12/16/2022 | Partial Approval | EVAN COOPER |
| Insulation | 12/20/2022 | Corrections Issued | EVAN COOPER |
| Insulation | 12/23/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 12/27/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/3/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 1/3/2023 | Corrections Issued | EVAN COOPER |
| Shower Pan | 1/3/2023 | Approved | EVAN COOPER |
| Final | 5/18/2023 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 5/18/2023 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/19/2023 | SGSOV Not Ready | EVAN COOPER |
| BUILDING-Rough-Frame | 5/24/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 5/24/2023 | Approved | HERBERT GIRON |
| Final | 5/24/2023 | OK to Issue CofO | HERBERT GIRON |
| Footing/Foundation/Slab | 5/24/2023 | Approved | HERBERT GIRON |
| Green Building Final | 5/24/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 5/24/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 5/24/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 5/24/2023 | SGSOV Approved | HERBERT GIRON |
| Service/Power Release | 5/24/2023 | Approved | HERBERT GIRON |
| Smoke Detectors | 5/24/2023 | Approved | HERBERT GIRON |