3201 S CLUB DR 90064

Certificate Information: 3201 S CLUB DR 90064

Application / Permit
22014-30000-01056
Plan Check / Job No.
B22WL00931
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel to first and second floors of (e) 2-story SFD. Remove portion of first and second levels at rear and addition. No net new floor area.
Permit Issued
Issued on 5/11/2022
Issuing Office
Current Status
CofO Issued on 5/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 JASON JANGADA
Corrections Issued 3/12/2022 JASON JANGADA
Applicant returned to address corrections 4/12/2022 JASON JANGADA
Plan Check Approved 4/25/2022 SAMUEL GONZALEZ
Issued 5/11/2022 APPLICANT
Building Plans Picked Up 5/16/2022 APPLICANT
CofO in Progress 5/22/2023 CLAYTON GRAHAM
Permit Finaled 5/24/2023 DANIEL ORRANTE
CofO Issued 5/24/2023 DANIEL ORRANTE
Permit Finaled 5/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 3/22/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 3/29/2022 JENSON LEE
Roof/Waste drainage to street Cleared 3/29/2022 JENSON LEE
Grading Pre-Inspection Cleared 4/1/2022 KIRK LINKLATER

Contact Information

Architect Strumwasser,, Scott Mark; Lic. No.: C21151 5971 W THIRD STREET      LOS ANGELES, CA 90036
Contractor Krumm Mike Construction Inc; Lic. No.: 915844-B 947 CALLE LOS ACEITUNOS      CAMARILLO, CA 93010
Engineer Vinci,, James Richard; Lic. No.: S4411 175 E WILBUR ROAD STE 103      THOUSAND OAKS, CA 91360

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/8/2022 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/26/2022 Partial Approval JOHN KIDWELL
Green Building Rough 8/26/2022 Partial Approval JOHN KIDWELL
Rough-Elec/Plmb/HVAC 12/9/2022 Partial Inspection OGANES TARAKHCHYAN
Special/Order Compliance 12/9/2022 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 12/16/2022 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 12/20/2022 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 12/21/2022 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/4/2023 Not Ready for Inspection JOHNNY MIRANDA
Green Building Rough 1/4/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 1/4/2023 Approved JOHNNY MIRANDA
Wood Frame 1/6/2023 Corrections Issued OGANES TARAKHCHYAN
Drywall Nailing 1/17/2023 Corrections Issued ASHLEY THOMPSON
Green Building Rough 1/17/2023 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 1/17/2023 Not Ready for Inspection ASHLEY THOMPSON
BUILDING-Rough-Frame 1/18/2023 Approved OGANES TARAKHCHYAN
Green Building Rough 1/18/2023 Approved OGANES TARAKHCHYAN
Insulation 1/18/2023 Approved OGANES TARAKHCHYAN
Drywall Nailing 1/20/2023 Conditional Approval ASHLEY THOMPSON
Interior/Exterior Lathing 1/20/2023 Partial Approval ASHLEY THOMPSON
Drywall Nailing 3/29/2023 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 3/29/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Final 5/11/2023 Not Ready for Inspection CLAYTON GRAHAM
Gas Test 5/11/2023 Approved CLAYTON GRAHAM
HVAC-Final 5/11/2023 Not Ready for Inspection CLAYTON GRAHAM
PLUMBING-Final 5/11/2023 Approved CLAYTON GRAHAM
ELECTRICAL-Final 5/15/2023 Corrections Issued CLAYTON GRAHAM
Final 5/15/2023 Not Ready for Inspection CLAYTON GRAHAM
Footing/Foundation/Slab 5/15/2023 Approved CLAYTON GRAHAM
Green Building Final 5/15/2023 Corrections Issued CLAYTON GRAHAM
HVAC-Final 5/15/2023 Approved CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 5/15/2023 SGSOV Approved CLAYTON GRAHAM
Smoke Detectors 5/15/2023 Approved CLAYTON GRAHAM
ELECTRICAL-Final 5/18/2023 Approved CLAYTON GRAHAM
Final 5/18/2023 OK to Issue CofO CLAYTON GRAHAM
Green Building Final 5/18/2023 Approved CLAYTON GRAHAM