3641 N DELLVALE PL 91436
Certificate Information: 3641 N DELLVALE PL 91436
- Application / Permit
- 22014-30000-01015
- Plan Check / Job No.
- B22WL00893
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 story addition to an existing 2-stoy sfd with attached garage
- Permit Issued
- Issued on 2/14/2023
- Issuing Office
- Valley
- Current Status
- Issued on 2/14/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | TARIK SAOUD |
| Corrections Issued | 4/4/2022 | TARIK SAOUD |
| Quality Review Completed | 4/14/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 10/4/2022 | YASHAR EMAMI |
| Building Plans Picked Up | 11/8/2022 | APPLICANT |
| Applicant returned to address corrections | 11/15/2022 | YASHAR EMAMI |
| Plan Check Approved | 11/29/2022 | YASHAR EMAMI |
| Issued | 2/14/2023 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/9/2022 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 5/9/2022 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 5/9/2022 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 5/9/2022 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 5/9/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/9/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2022 | COLIN LOREDO |
| Specific Plan | Cleared | 10/18/2022 | OLGA AYALA |
| ZA Case | Cleared | 10/18/2022 | OLGA AYALA |
| Hydrant and Access approval | Cleared | 10/22/2022 | RUEL COLE |
| Low Impact Development | Cleared | 11/1/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 11/1/2022 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 11/15/2022 | TARIK SAOUD |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 9/8/2023 | Corrections Issued | VINCENT HANLEY |
| Special/Order Compliance | 8/22/2024 | Corrections Issued | THOMAS FINNILA |
| Piling/Pier/Caisson | 11/25/2024 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 1/31/2025 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/19/2025 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/28/2025 | Corrections Issued | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 3/17/2025 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/17/2025 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2025 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 6/21/2025 | Partial Inspection | RYAN SALAZAR |
| Wood Frame | 6/21/2025 | Partial Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 8/9/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 8/9/2025 | Partial Approval | GEVORK IPCHYAN |
| PLUMBING-Rough | 8/9/2025 | Partial Approval | GEVORK IPCHYAN |
| Wood Frame | 8/9/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2025 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 8/16/2025 | Partial Approval | DAVID ANDERSON |
| Special/Order Compliance | 8/16/2025 | Corrections Issued | DAVID ANDERSON |
| Wood Frame | 8/16/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Deputy Wood Construction | 11/4/2025 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Gas Test | 12/6/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Sewer | 12/6/2025 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 12/6/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 12/6/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |