575 N ERSKINE DR 90272

Certificate Information: 575 N ERSKINE DR 90272

Application / Permit
22014-30000-01012
Plan Check / Job No.
B22WL00889
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Second floor addition to enlarge master bedroom, balcony remodel.
Permit Issued
Issued on 6/9/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 JAHANSHAH POURHASSAN
Corrections Issued 3/30/2022 JAHANSHAH POURHASSAN
Quality Review Completed 4/4/2022 CHIHARU SUZUKI
Building Plans Picked Up 4/4/2022 APPLICANT
Plan Check Approved 11/3/2022 JAHANSHAH POURHASSAN
Issued 6/9/2023 APPLICANT
CofO in Progress 1/25/2024 EVAN COOPER
Permit Finaled 2/27/2024 DANIEL ORRANTE
CofO Issued 2/27/2024 DANIEL ORRANTE
Permit Finaled 2/27/2024 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/20/2022 CINDY JOSSELYN
Grading Pre-Inspection Cleared 5/25/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 10/3/2022 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 10/3/2022 ANTHONY MAINEZ
Coastal Zone Cleared 10/21/2022 STEVEN WECHSLER

Contact Information

Architect Gray,, Melinda; Lic. No.: C18171 639 E CHANNEL ROAD      SANTA MONICA, CA 90402
Contractor Gleicher Associates Inc; Lic. No.: 759307-B 415 SOUTH TOPANGA CANYON BLVD      TOPANGA, CA 90290
Engineer Perazzelli,, Joseph Ames; Lic. No.: C35270 183 GREENFIELD AVENUE      LOS ANGELES, CA 90049

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 7/26/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 8/31/2023 No Access for Inspection KENNETH NAGLE
ELECTRICAL-Rough 9/1/2023 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/1/2023 Partial Approval EVAN COOPER
Green Building Rough 9/1/2023 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 10/11/2023 Approved EVAN COOPER
Green Building Rough 10/11/2023 Approved EVAN COOPER
Interior/Exterior Lathing 10/11/2023 Approved EVAN COOPER
Wood Frame 10/11/2023 Approved EVAN COOPER
Insulation 10/16/2023 Approved EVAN COOPER
Drywall Nailing 10/19/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 1/22/2024 Approved EVAN COOPER
ELECTRICAL-Final 1/22/2024 Approved EVAN COOPER
Final 1/22/2024 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 1/22/2024 Approved EVAN COOPER
Green Building Final 1/22/2024 Approved EVAN COOPER
HVAC-Final 1/22/2024 Approved EVAN COOPER
PLUMBING-Final 1/22/2024 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/22/2024 SGSOV Approved EVAN COOPER
Smoke Detectors 1/22/2024 Approved EVAN COOPER
Final 1/24/2024 Conditional Approval EVAN COOPER
Final 1/25/2024 OK to Issue CofO EVAN COOPER