575 N ERSKINE DR 90272
Certificate Information: 575 N ERSKINE DR 90272
- Application / Permit
- 22014-30000-01012
- Plan Check / Job No.
- B22WL00889
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Second floor addition to enlarge master bedroom, balcony remodel.
- Permit Issued
- Issued on 6/9/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | JAHANSHAH POURHASSAN |
| Corrections Issued | 3/30/2022 | JAHANSHAH POURHASSAN |
| Quality Review Completed | 4/4/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 4/4/2022 | APPLICANT |
| Plan Check Approved | 11/3/2022 | JAHANSHAH POURHASSAN |
| Issued | 6/9/2023 | APPLICANT |
| CofO in Progress | 1/25/2024 | EVAN COOPER |
| Permit Finaled | 2/27/2024 | DANIEL ORRANTE |
| CofO Issued | 2/27/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/27/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/20/2022 | CINDY JOSSELYN |
| Grading Pre-Inspection | Cleared | 5/25/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 10/3/2022 | ANTHONY MAINEZ |
| Coastal Zone | Cleared | 10/21/2022 | STEVEN WECHSLER |
Contact Information
| Architect | Gray,, Melinda; Lic. No.: C18171 | 639 E CHANNEL ROAD SANTA MONICA, CA 90402 |
| Contractor | Gleicher Associates Inc; Lic. No.: 759307-B | 415 SOUTH TOPANGA CANYON BLVD TOPANGA, CA 90290 |
| Engineer | Perazzelli,, Joseph Ames; Lic. No.: C35270 | 183 GREENFIELD AVENUE LOS ANGELES, CA 90049 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 7/26/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Deputy Wood Construction | 8/31/2023 | No Access for Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 9/1/2023 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Partial Approval | EVAN COOPER |
| Green Building Rough | 9/1/2023 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 10/11/2023 | Approved | EVAN COOPER |
| Green Building Rough | 10/11/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 10/11/2023 | Approved | EVAN COOPER |
| Wood Frame | 10/11/2023 | Approved | EVAN COOPER |
| Insulation | 10/16/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 10/19/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 1/22/2024 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 1/22/2024 | Approved | EVAN COOPER |
| Final | 1/22/2024 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 1/22/2024 | Approved | EVAN COOPER |
| Green Building Final | 1/22/2024 | Approved | EVAN COOPER |
| HVAC-Final | 1/22/2024 | Approved | EVAN COOPER |
| PLUMBING-Final | 1/22/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 1/22/2024 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 1/22/2024 | Approved | EVAN COOPER |
| Final | 1/24/2024 | Conditional Approval | EVAN COOPER |
| Final | 1/25/2024 | OK to Issue CofO | EVAN COOPER |