3582 S MILITARY AVE 90034
Certificate Information: 3582 S MILITARY AVE 90034
- Application / Permit
- 22014-30000-00975
- Plan Check / Job No.
- B22WL00843
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ground floor and 2nd story addition to (e) S.F.D. remove (e) driveway
- Permit Issued
- Issued on 7/26/2022
- Issuing Office
- Current Status
- CofO Issued on 11/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | YASHAR EMAMI |
| Corrections Issued | 3/17/2022 | YASHAR EMAMI |
| Quality Review Completed | 3/18/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 4/6/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 6/10/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 7/7/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 7/19/2022 | YASHAR EMAMI |
| Plan Check Approved | 7/21/2022 | YASHAR EMAMI |
| Issued | 7/26/2022 | APPLICANT |
| Building Plans Picked Up | 7/27/2022 | APPLICANT |
| CofO in Progress | 11/28/2023 | JESUS PINEDA |
| Permit Finaled | 11/29/2023 | DANIEL ORRANTE |
| CofO Issued | 11/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/30/2022 | KIRK LINKLATER |
| Drainage to Storm Drain | Cleared | 3/31/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2022 | SAUL GARCIA |
| Permit | Cleared | 3/31/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 3/31/2022 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 4/1/2022 | KIRK LINKLATER |
| Disturb/Remove Protected Trees | Cleared | 4/20/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 4/29/2022 | MICHAEL GILLISSIE |
| Trees in Parkway | Cleared | 5/4/2022 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 5/19/2022 | JENSON LEE |
| GPI Written Notices | Cleared | 7/7/2022 | YASHAR EMAMI |
Contact Information
| Architect | Perazzelli,, Francesca; Lic. No.: C13717 | 183 GREENFIELD AVENUE LOS ANGELES, CA 90049 |
| Contractor | Martinko Construction Inc; Lic. No.: 990964-B | 10372 KESWICK AVENUE LOS ANGELES, CA 90064 |
| Engineer | Perazzelli,, Joseph Ames; Lic. No.: C35270 | 183 GREENFIELD AVENUE LOS ANGELES, CA 90049 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/25/2022 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 8/29/2022 | Approved | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 9/2/2022 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 9/19/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 9/19/2022 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 9/19/2022 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/22/2022 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 11/28/2022 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/7/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Gas Test | 12/7/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 12/7/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 12/12/2022 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2022 | Partial Approval | JOHNNY MIRANDA |
| Gas Test | 12/12/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 12/12/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 12/13/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 12/13/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 12/13/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 12/13/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 1/12/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/12/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 1/13/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/13/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 1/24/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 1/24/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 8/10/2023 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 8/10/2023 | Not Ready for Inspection | JESUS PINEDA |
| Final | 8/10/2023 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 8/10/2023 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Final | 8/10/2023 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Final | 8/10/2023 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Final | 8/10/2023 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 8/10/2023 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Final | 10/16/2023 | Corrections Issued | MICHAEL PELHAM |
| Final | 10/16/2023 | Corrections Issued | MICHAEL PELHAM |
| Footing/Foundation/Slab | 10/16/2023 | Approved | MICHAEL PELHAM |
| Green Building Final | 10/16/2023 | Approved | MICHAEL PELHAM |
| HVAC-Final | 10/16/2023 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Final | 10/16/2023 | Approved | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Approved | MICHAEL PELHAM |
| Smoke Detectors | 10/16/2023 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Final | 11/27/2023 | Approved | JESUS PINEDA |
| Final | 11/27/2023 | OK to Issue CofO | JESUS PINEDA |
| HVAC-Final | 11/27/2023 | Approved | JESUS PINEDA |
| Service/Power Release | 11/27/2023 | Approved | JESUS PINEDA |