489 S DENSLOW AVE 90049

Certificate Information: 489 S DENSLOW AVE 90049

Application / Permit
22014-30000-00941
Plan Check / Job No.
B22WL00785
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
remove existing 260 sf 2nd floor deck and install a new 485 sf deck/patio cover
Permit Issued
Issued on 9/24/2022
Issuing Office
Current Status
Issued on 9/24/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/2/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 HOOMAN HAJIZADEH
Corrections Issued 4/4/2022 HOOMAN HAJIZADEH
Quality Review Completed 4/14/2022 CHIHARU SUZUKI
Applicant returned to address corrections 7/14/2022 HOOMAN HAJIZADEH
Applicant returned to address corrections 8/26/2022 HOOMAN HAJIZADEH
Plan Check Approved 8/26/2022 HOOMAN HAJIZADEH
Issued 9/24/2022 APPLICANT
Building Plans Picked Up 9/29/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/10/2022 DINAH GARIN
Low Impact Development Cleared 5/19/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/2/2022 DINAH GARIN
GPI Written Notices Cleared 7/14/2022 HOOMAN HAJIZADEH
Grading Pre-Inspection Cleared 7/14/2022 HOOMAN HAJIZADEH

Contact Information

Contractor S O S Enterprises Inc; Lic. No.: 696896-B 2355 WESTWOOD BLVD #201      LOS ANGELES, CA 90064
Engineer Onishi,, Robert K; Lic. No.: S3705 4438 LINDBLADE DRIVE      LOS ANGELES, CA 90066

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/30/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/6/2022 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 10/14/2022 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 10/20/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 5/31/2023 Partial Approval CARLOS MATAMOROS
Final 5/31/2023 Corrections Issued CARLOS MATAMOROS
Green Building Final 5/31/2023 Approved CARLOS MATAMOROS
Green Building Rough 5/31/2023 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 5/31/2023 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 5/31/2023 Not Ready for Inspection CARLOS MATAMOROS