4820 S COOLIDGE AVE 90230
Certificate Information: 4820 S COOLIDGE AVE 90230
- Application / Permit
- 22014-30000-00936
- Plan Check / Job No.
- B22WL00775
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- substantial demolition of site and existing single story family residence and construction of a two story S.F.R., roof deck. *** 1 of 2 ***
- Permit Issued
- Issued on 10/14/2022
- Issuing Office
- Current Status
- Issued on 10/14/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | KAVIAN REFAHI |
| Corrections Issued | 3/17/2022 | KAVIAN REFAHI |
| Quality Review Completed | 3/25/2022 | FELIX FIGUEROA |
| Applicant returned to address corrections | 7/14/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 8/5/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 8/8/2022 | KAVIAN REFAHI |
| Plan Check Approved | 8/8/2022 | KAVIAN REFAHI |
| Issued | 10/14/2022 | APPLICANT |
| Building Plans Picked Up | 10/26/2022 | APPLICANT |
Permit Application Clearance Information
| Permit | Cleared | 4/23/2022 | STEVEN JIN |
| Sewer availability | Cleared | 4/23/2022 | STEVEN JIN |
| Trees in Parkway | Cleared | 6/17/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 8/4/2022 | CHRIS VONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 8/5/2022 | ANTHONY MAINEZ |
Contact Information
| Contractor | Crescenta Valley Engineering Inc; Lic. No.: 523164-B | 2801 E FOOTHILL BLVD PASADENA, CA 91107 |
| Engineer | Attaalla,, Sayed Ahmed; Lic. No.: S5339 | 11254 HANNUM AVE CULVER CITY, CA 90230 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/6/2022 | No Access for Inspection | JESUS RODRIGUEZ |
| Pre-Inspection | 12/12/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 6/13/2023 | Partial Approval | JESUS RODRIGUEZ |
| Structural Steel Frame | 7/27/2023 | Conditional Approval | HERBERT GIRON |
| Deputy Drilled-In Anchors | 8/2/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/4/2023 | Corrections Issued | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 8/8/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/8/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/1/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/22/2023 | Approved | TEMISTOCLES CAAL |
| Insulation | 9/26/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2023 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Steel/Welding | 12/7/2023 | Conditional Approval | RICHARD STEINBACH |
| Structural Steel Frame | 12/13/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Deputy Wood Construction | 7/2/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 7/9/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/16/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 5/12/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 5/12/2025 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Rough | 8/5/2025 | Corrections Issued | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 8/5/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 8/5/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 8/19/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Corrections Issued | RUBEN RIVAS |
| HVAC-Rough | 9/2/2025 | Not Ready for Inspection | RUBEN RIVAS |
| HVAC-Rough | 9/5/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 9/23/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Rough | 9/23/2025 | Partial Approval | WILBER ROSALES |
| MERV13>=Rough | 9/23/2025 | Approved | WILBER ROSALES |
| Verify Sprinkler Sign Off | 9/23/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 10/15/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 10/15/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 10/15/2025 | Partial Approval | WILBER ROSALES |
| Insulation | 10/28/2025 | Corrections Issued | RUBEN RIVAS |
| Insulation | 10/31/2025 | Approved | WILBER ROSALES |
| Drywall Nailing | 11/7/2025 | Approved | RUBEN RIVAS |
| Shower Pan | 12/17/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 1/15/2026 | Approved | DAKOTA LOW |
| Shower Pan | 1/15/2026 | Approved | DAKOTA LOW |