1053 E NOWITA PL 90291

Certificate Information: 1053 E NOWITA PL 90291

Application / Permit
22014-30000-00926
Plan Check / Job No.
B22WL00765
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new 2 story addition to (e) S.F.R. remodel with a new attached carport
Permit Issued
Issued on 7/18/2022
Issuing Office
Current Status
CofO Issued on 7/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 TARIK SAOUD
Corrections Issued 3/17/2022 TARIK SAOUD
Quality Review Completed 3/21/2022 CHIHARU SUZUKI
Plan Check Approved 4/25/2022 TARIK SAOUD
Building Plans Picked Up 7/5/2022 APPLICANT
Issued 7/18/2022 APPLICANT
CofO in Progress 6/28/2024 HERBERT GIRON
Permit Finaled 7/6/2024 DANIEL ORRANTE
CofO Issued 7/6/2024 DANIEL ORRANTE
Permit Finaled 7/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 3/22/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 3/23/2022 DINAH GARIN
Sewer availability Cleared 3/23/2022 DINAH GARIN
Specific Plan Cleared 3/29/2022 VALERIA CEJA
Low Impact Development Cleared 4/13/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 4/18/2022 DINAH GARIN

Contact Information

Architect Myer,, Jamie Beekman; Lic. No.: C31042 1730 3/4 WESTWOOD BLVD      LOS ANGELES, CA 90024
Contractor Shenon Construction; Lic. No.: 939809-B 1420 N ALTA VISTA BLVD #404      LOS ANGELES, CA 90046
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/7/2022 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/9/2022 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 9/14/2022 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 9/19/2022 Approved DAVID FEILER
Footing/Foundation/Slab 9/19/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Partial Approval DAVID FEILER
Deputy Wood Construction 11/9/2022 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Partial Approval EVAN COOPER
Special/Order Compliance 12/5/2022 Partial Inspection JEREMY TODD
ELECTRICAL-Rough 1/31/2023 Approved EVAN COOPER
Green Building Rough 1/31/2023 Approved EVAN COOPER
HVAC-Rough 1/31/2023 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 1/31/2023 Partial Approval EVAN COOPER
PLUMBING-Rough 1/31/2023 Approved EVAN COOPER
Wood Frame 1/31/2023 Approved EVAN COOPER
Insulation 2/2/2023 Corrections Issued HERBERT GIRON
Shower Pan 2/7/2023 Partial Approval EVAN COOPER
Interior/Exterior Lathing 2/10/2023 Partial Approval EVAN COOPER
Drywall Nailing 3/1/2023 Approved EVAN COOPER
Shower Pan 3/8/2023 Approved EVAN COOPER
Interior/Exterior Lathing 3/13/2023 Approved EVAN COOPER
Interior/Exterior Lathing 8/9/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 10/25/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 10/25/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 10/25/2023 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 10/25/2023 Corrections Issued HERBERT GIRON
Special/Order Compliance 10/26/2023 Corrections Issued RICHARD STEINBACH
ELECTRICAL-Final 11/30/2023 Approved HERBERT GIRON
Service/Power Release 11/30/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 4/10/2024 Approved HERBERT GIRON
Final 4/10/2024 Corrections Issued HERBERT GIRON
Green Building Final 4/10/2024 Approved HERBERT GIRON
HVAC-Final 4/10/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 4/10/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 4/10/2024 Approved HERBERT GIRON
Verify Sprinkler Sign Off 4/10/2024 Approved HERBERT GIRON
Final 4/18/2024 Not Ready for Inspection HERBERT GIRON
HVAC-Final 4/18/2024 Corrections Issued HERBERT GIRON
Final 4/22/2024 Corrections Issued HERBERT GIRON
HVAC-Final 4/22/2024 Approved HERBERT GIRON
Final 6/27/2024 OK to Issue CofO HERBERT GIRON