14011 W HESBY ST 91423
Certificate Information: 14011 W HESBY ST 91423
- Application / Permit
- 22014-30000-00884
- Plan Check / Job No.
- B22WL00748
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) Garage to ADU w/ 2nd Story Addition per LAMC 12.22 A.33 (c) and (d)
- Permit Issued
- Issued on 6/16/2022
- Issuing Office
- Current Status
- CofO Issued on 1/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | DAVID CASTILLO |
| Corrections Issued | 4/1/2022 | DAVID CASTILLO |
| Quality Review Completed | 4/18/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 6/8/2022 | DAVID CASTILLO |
| Issued | 6/16/2022 | APPLICANT |
| Building Plans Picked Up | 6/22/2022 | APPLICANT |
| CofO in Progress | 1/12/2023 | MISAEL ESPARZA |
| Permit Finaled | 1/19/2023 | MICHAEL SMITH |
| CofO Issued | 1/19/2023 | MICHAEL SMITH |
| Permit Finaled | 1/19/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/6/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 4/6/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 4/7/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 5/23/2022 | RIDWAN HARDY |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/24/2022 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 6/27/2022 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 6/29/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2022 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 7/20/2022 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 7/21/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/22/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/26/2022 | Approved | MISAEL ESPARZA |
| Sewer | 7/26/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 7/29/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 8/3/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2022 | Corrections Issued | MISAEL ESPARZA |
| Shower Pan | 8/8/2022 | Partial Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 8/18/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/1/2022 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 9/1/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/8/2022 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/20/2022 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 9/20/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/27/2022 | Approved | MISAEL ESPARZA |
| Insulation | 9/27/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 10/5/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 10/13/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 12/13/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 12/13/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/19/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 12/19/2022 | Corrections Issued | MISAEL ESPARZA |
| Service/Power Release | 12/19/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 1/5/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 1/5/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/5/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 1/5/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 1/11/2023 | Approved | MISAEL ESPARZA |
| Final | 1/11/2023 | OK to Issue CofO | MISAEL ESPARZA |
| HVAC-Final | 1/11/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 1/11/2023 | Approved | MISAEL ESPARZA |
| Service/Power Release | 1/11/2023 | Approved | MISAEL ESPARZA |