4237 S TIVOLI AVE 90066
Certificate Information: 4237 S TIVOLI AVE 90066
- Application / Permit
- 22014-30000-00832
- Plan Check / Job No.
- B22WL00736
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION TO (E) SFD
- Permit Issued
- Issued on 6/3/2022
- Issuing Office
- Current Status
- CofO Issued on 9/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | EDWIN ESPIN |
| Corrections Issued | 3/7/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 4/26/2022 | JASON JANGADA |
| Plan Check Approved | 5/11/2022 | RICHARD GARCIA |
| Issued | 6/3/2022 | APPLICANT |
| Building Plans Picked Up | 6/6/2022 | APPLICANT |
| Refund in Progress | 5/31/2023 | SELENIA GARCIA |
| Refund Denied | 7/6/2023 | EMILY HU |
| Issued | 7/6/2023 | EMILY HU |
| CofO in Progress | 8/30/2024 | JESUS PINEDA |
| CofO in Progress | 8/30/2024 | JESUS PINEDA |
| CofO in Progress | 8/30/2024 | JESUS PINEDA |
| Permit Finaled | 9/4/2024 | RICHARD STEINBACH |
| CofO Issued | 9/4/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/4/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 5/4/2022 | JENSON LEE |
| Sewer availability | Cleared | 5/4/2022 | JENSON LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/31/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 6/5/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/5/2024 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 6/7/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 7/8/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 7/8/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 7/8/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/8/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 7/10/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 7/10/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/11/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 7/12/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 7/12/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 7/12/2024 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 7/22/2024 | Not Ready for Inspection | HERBERT GIRON |
| Final | 8/22/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 8/22/2024 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 8/22/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/28/2024 | Approved | TEMISTOCLES CAAL |
| Final | 8/28/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 8/28/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Final | 8/28/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 8/28/2024 | Approved | TEMISTOCLES CAAL |
| Final | 8/30/2024 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 8/30/2024 | Approved | JESUS PINEDA |
| Service/Power Release | 8/30/2024 | Approved | JESUS PINEDA |
| Service/Power Release | 9/4/2024 | Approved | JESUS PINEDA |