4237 S TIVOLI AVE 90066

Certificate Information: 4237 S TIVOLI AVE 90066

Application / Permit
22014-30000-00832
Plan Check / Job No.
B22WL00736
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO (E) SFD
Permit Issued
Issued on 6/3/2022
Issuing Office
Current Status
CofO Issued on 9/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 EDWIN ESPIN
Corrections Issued 3/7/2022 EDWIN ESPIN
Applicant returned to address corrections 4/26/2022 JASON JANGADA
Plan Check Approved 5/11/2022 RICHARD GARCIA
Issued 6/3/2022 APPLICANT
Building Plans Picked Up 6/6/2022 APPLICANT
Refund in Progress 5/31/2023 SELENIA GARCIA
Refund Denied 7/6/2023 EMILY HU
Issued 7/6/2023 EMILY HU
CofO in Progress 8/30/2024 JESUS PINEDA
CofO in Progress 8/30/2024 JESUS PINEDA
CofO in Progress 8/30/2024 JESUS PINEDA
Permit Finaled 9/4/2024 RICHARD STEINBACH
CofO Issued 9/4/2024 RICHARD STEINBACH
Permit Finaled 9/4/2024 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/4/2022 JENSON LEE
Roof/Waste drainage to street Cleared 5/4/2022 JENSON LEE
Sewer availability Cleared 5/4/2022 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/31/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 6/5/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 6/5/2024 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/7/2024 Approved JESUS RODRIGUEZ
Insulation 6/7/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Rough 7/8/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/8/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 7/8/2024 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 7/8/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 7/8/2024 Approved JESUS RODRIGUEZ
Insulation 7/10/2024 Approved JESUS RODRIGUEZ
Shower Pan 7/10/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 7/11/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/12/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 7/12/2024 Approved JESUS RODRIGUEZ
Green Building Rough 7/12/2024 Approved JESUS RODRIGUEZ
Service/Power Release 7/22/2024 Not Ready for Inspection HERBERT GIRON
Final 8/22/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Final 8/22/2024 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/22/2024 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 8/22/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 8/28/2024 Approved TEMISTOCLES CAAL
Final 8/28/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 8/28/2024 Not Ready for Inspection TEMISTOCLES CAAL
HVAC-Final 8/28/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 8/28/2024 Approved TEMISTOCLES CAAL
Final 8/30/2024 OK to Issue CofO JESUS PINEDA
Green Building Final 8/30/2024 Approved JESUS PINEDA
Service/Power Release 8/30/2024 Approved JESUS PINEDA
Service/Power Release 9/4/2024 Approved JESUS PINEDA