7800 S AIRLANE AVE 90045

Certificate Information: 7800 S AIRLANE AVE 90045

Application / Permit
22014-30000-00806
Plan Check / Job No.
B22WL00729
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT BASEMENT AND ATTACHED GARAGE INTO ACCESORY DWELLING UNIT (ADU), 1ST LFOOR ADDITION TO SINGLE FAMILY DWELLING, AND RAISED COVERED PATIO AT FRONT, AND NEW ATTACHED DECK AT REAR. ADU PER CA GOVERNMENT CODE 65852.2(e)(1)(A)
Permit Issued
Issued on 11/16/2022
Issuing Office
Valley
Current Status
CofO Corrected on 1/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 FELIPE HERNANDEZ
Corrections Issued 3/7/2022 FELIPE HERNANDEZ
Quality Review Completed 3/16/2022 CHIHARU SUZUKI
Applicant returned to address corrections 6/14/2022 FELIPE HERNANDEZ
Applicant returned to address corrections 9/9/2022 SERGIO SILVA
Applicant returned to address corrections 10/24/2022 SERGIO SILVA
Plan Check Approved 11/1/2022 SERGIO SILVA
Building Plans Picked Up 11/10/2022 APPLICANT
Issued 11/16/2022 APPLICANT
CofO in Progress 12/21/2023 BOBBY KEY
CofO Issued-Status Void 12/26/2023 DANIEL ORRANTE
Permit Finaled-Status Void 12/26/2023 DANIEL ORRANTE
Re-Activate Permit 1/12/2024 DANIEL ORRANTE
Permit Finaled 1/22/2024 DANIEL ORRANTE
Permit Finaled 1/22/2024 DANIEL ORRANTE
CofO Corrected 1/22/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/24/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 3/25/2022 DINAH GARIN
Sewer availability Cleared 3/25/2022 DINAH GARIN
Low Impact Development Cleared 8/1/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/2/2022 DINAH GARIN
Grading Pre-Inspection Cleared 8/16/2022 MICHAEL TEMPLE
Specific Plan Cleared 10/17/2022 EDUARDO HERMOSO
GPI Written Notices Cleared 11/1/2022 FELIPE HERNANDEZ

Contact Information

Architect Heeb,, Derek M; Lic. No.: C32338 406 BROADWAY 222C      SANTA MONICA, CA 90401
Contractor Nittay Inc; Lic. No.: 1033506-B 17941 VENTURA BLVD #204      ENCINO, CA 91316
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/14/2022 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 12/14/2022 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 1/13/2023 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 1/20/2023 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 1/25/2023 Partial Approval BOBBY KEY
Deputy Drilled-In Anchors 2/2/2023 Approved BOBBY KEY
Footing/Foundation/Slab 2/2/2023 Approved BOBBY KEY
Reinforced Concrete Frame 2/8/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Partial Approval BOBBY KEY
Deputy Drilled-In Anchors 3/28/2023 Conditional Approval BOBBY KEY
HVAC-Rough 4/5/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 4/5/2023 Approved BOBBY KEY
Shower Pan 4/12/2023 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 4/17/2023 Partial Approval RICHARD STEINBACH
Shower Pan 4/17/2023 Approved RICHARD STEINBACH
ELECTRICAL-Rough 4/20/2023 Approved BOBBY KEY
HVAC-Rough 4/20/2023 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 4/25/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Corrections Issued BOBBY KEY
HVAC-Rough 4/25/2023 Approved BOBBY KEY
Deputy Wood Construction 4/27/2023 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/16/2023 Partial Approval BOBBY KEY
Interior/Exterior Lathing 5/16/2023 Partial Approval BOBBY KEY
Insulation 5/18/2023 Approved BOBBY KEY
Deputy Wood Construction 5/19/2023 Conditional Approval HERBERT GIRON
BUILDING-Rough-Frame 5/22/2023 Approved BOBBY KEY
Deputy Wood Construction 5/22/2023 Approved BOBBY KEY
Green Building Rough 5/22/2023 Approved BOBBY KEY
Drywall Nailing 5/25/2023 Not Ready for Inspection RICHARD STEINBACH
Drywall Nailing 5/31/2023 Approved RICHARD STEINBACH
Sewer 6/16/2023 Not Ready for Inspection BOBBY KEY
Underground Mechanical 6/16/2023 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 9/7/2023 Approved BOBBY KEY
Final 9/7/2023 Corrections Issued BOBBY KEY
Green Building Final 9/7/2023 Approved BOBBY KEY
HVAC-Final 9/7/2023 Corrections Issued BOBBY KEY
PLUMBING-Final 9/7/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/7/2023 SGSOV Approved BOBBY KEY
Service/Power Release 9/7/2023 Approved BOBBY KEY
Smoke Detectors 9/7/2023 Approved BOBBY KEY
Final 12/21/2023 OK to Issue CofO BOBBY KEY
HVAC-Final 12/21/2023 Approved BOBBY KEY