7723 W 79TH ST 90293
Certificate Information: 7723 W 79TH ST 90293
- Application / Permit
- 22014-30000-00710
- Plan Check / Job No.
- B22WL00664
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel throughout and ground floor addition to first flor of a 2-story S.F.D.
- Permit Issued
- Issued on 5/17/2022
- Issuing Office
- Current Status
- CofO Issued on 11/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2022 | EDWIN ESPIN |
| Corrections Issued | 3/1/2022 | EDWIN ESPIN |
| Plan Check Approved | 4/8/2022 | EDWIN ESPIN |
| Issued | 5/17/2022 | APPLICANT |
| Building Plans Picked Up | 5/26/2022 | APPLICANT |
| CofO in Progress | 10/26/2022 | BOBBY KEY |
| Permit Finaled | 11/3/2022 | DANIEL ORRANTE |
| CofO Issued | 11/3/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/3/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/24/2022 | SERGIO VALENZUELA |
| Roof/Waste drainage to street | Cleared | 3/29/2022 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2022 | DENNIS BRAGIN |
Contact Information
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: C72927 | 560 31ST ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/13/2022 | Conditional Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 7/14/2022 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 7/14/2022 | Not Ready for Inspection | DAVID FEILER |
| METHANE-Barrier | 7/14/2022 | Approved | DAVID FEILER |
| METHANE-Subgrade | 7/14/2022 | Approved | DAVID FEILER |
| PLUMBING-Rough | 7/14/2022 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 8/8/2022 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/8/2022 | Approved | BOBBY KEY |
| Green Building Rough | 8/8/2022 | Not Ready for Inspection | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 8/8/2022 | Approved | BOBBY KEY |
| Deputy Wood Construction | 8/10/2022 | Conditional Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 8/11/2022 | Conditional Approval | BOBBY KEY |
| Green Building Rough | 8/11/2022 | Conditional Approval | BOBBY KEY |
| Interior/Exterior Lathing | 8/11/2022 | Partial Approval | BOBBY KEY |
| Insulation | 8/15/2022 | Conditional Approval | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 8/15/2022 | Partial Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 8/17/2022 | Not Ready for Inspection | BOBBY KEY |
| Insulation | 8/17/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/17/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 8/19/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 8/19/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/14/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 10/14/2022 | Approved | BOBBY KEY |
| Final | 10/14/2022 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 10/14/2022 | Approved | BOBBY KEY |
| HVAC-Final | 10/14/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 10/14/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/14/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 10/14/2022 | Approved | BOBBY KEY |
| Final | 10/26/2022 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 10/26/2022 | Approved | BOBBY KEY |