7901 S DUNBARTON AVE 90045

Certificate Information: 7901 S DUNBARTON AVE 90045

Application / Permit
22014-30000-00677
Plan Check / Job No.
B22WL00630
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel (keeping portion of existing conc. foundation & floor framing) to (E) 1-story SFD and second floor addition w/ new attached garage
Permit Issued
Issued on 9/12/2022
Issuing Office
Current Status
CofO Issued on 10/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 HOOMAN HAJIZADEH
Corrections Issued 3/17/2022 HOOMAN HAJIZADEH
Quality Review Completed 3/23/2022 CHIHARU SUZUKI
Applicant returned to address corrections 7/8/2022 HOOMAN HAJIZADEH
Applicant returned to address corrections 7/29/2022 HOOMAN HAJIZADEH
Applicant returned to address corrections 8/18/2022 HOOMAN HAJIZADEH
Plan Check Approved 8/19/2022 HOOMAN HAJIZADEH
Issued 9/12/2022 APPLICANT
Building Plans Picked Up 9/14/2022 APPLICANT
CofO in Progress 10/11/2024 BOBBY KEY
Permit Finaled 10/15/2024 RICHARD STEINBACH
CofO Issued 10/15/2024 RICHARD STEINBACH
Permit Finaled 10/15/2024 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 4/8/2022 STEVEN JIN
Low Impact Development Cleared 5/11/2022 TA ANH
Eng Process Fee Ord 176,300 Cleared 5/14/2022 STEVEN JIN
Roof/Waste drainage to street Cleared 5/14/2022 STEVEN JIN
Sewer availability Cleared 5/14/2022 STEVEN JIN
Trees in Parkway Cleared 6/1/2022 ADALBERTO VERA
Specific Plan Cleared 6/9/2022 PEDRO AYALA
GPI Written Notices Cleared 7/8/2022 HOOMAN HAJIZADEH
Grading Pre-Inspection Cleared 7/8/2022 HOOMAN HAJIZADEH

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/27/2022 Partial Inspection BOBBY KEY
Footing/Foundation/Slab 12/20/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 1/19/2023 Partial Approval HERBERT GIRON
PLUMBING-Rough 1/19/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Partial Approval BOBBY KEY
Special/Order Compliance 1/24/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 3/30/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Partial Approval BOBBY KEY
Interior/Exterior Lathing 4/10/2023 Partial Approval BOBBY KEY
Special/Order Compliance 4/21/2023 Partial Inspection BOBBY KEY
ELECTRICAL-Rough 7/14/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 7/14/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 7/14/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 7/18/2023 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 7/18/2023 Approved BOBBY KEY
Green Building Rough 7/18/2023 Approved BOBBY KEY
HVAC-Rough 7/18/2023 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 8/18/2023 Approved BOBBY KEY
Verify Sprinkler Sign Off 8/18/2023 Approved BOBBY KEY
Insulation 8/25/2023 Corrections Issued BOBBY KEY
Insulation 8/29/2023 Approved BOBBY KEY
Drywall Nailing 9/12/2023 Approved RICHARD STEINBACH
HVAC-Rough 9/28/2023 Approved BOBBY KEY
Interior/Exterior Lathing 9/28/2023 Partial Approval BOBBY KEY
Gas Test 10/16/2023 Approved BOBBY KEY
Interior/Exterior Lathing 10/16/2023 Approved BOBBY KEY
ELECTRICAL-Final 1/18/2024 Approved TEMISTOCLES CAAL
HVAC-Final 1/23/2024 Approved BOBBY KEY
PLUMBING-Final 1/23/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/23/2024 SGSOV Approved BOBBY KEY
Service/Power Release 1/25/2024 Approved BOBBY KEY
Final 10/11/2024 OK to Issue CofO BOBBY KEY
Green Building Final 10/11/2024 Approved BOBBY KEY
Smoke Detectors 10/11/2024 Approved BOBBY KEY