3929 S TIVOLI AVE 90066

Certificate Information: 3929 S TIVOLI AVE 90066

Application / Permit
22014-30000-00666
Plan Check / Job No.
B22WL00616
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
remodel of a S.F.R. throughout to include a addition
Permit Issued
Issued on 12/5/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 YASHAR EMAMI
Corrections Issued 3/25/2022 YASHAR EMAMI
Quality Review Completed 3/30/2022 CHIHARU SUZUKI
Building Plans Picked Up 4/12/2022 APPLICANT
Applicant returned to address corrections 6/14/2023 YASHAR EMAMI
Applicant returned to address corrections 10/4/2023 YASHAR EMAMI
Plan Check Approved 10/12/2023 YASHAR EMAMI
Issued 12/5/2023 APPLICANT
CofO in Progress 5/7/2026 DAKOTA LOW
Permit Finaled 5/11/2026 RICHARD STEINBACH
CofO Issued 5/11/2026 RICHARD STEINBACH
Permit Finaled 5/11/2026 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 7/13/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 7/14/2023 JASON NG
Sewer availability Cleared 7/14/2023 JASON NG
Low Impact Development Cleared 9/13/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 10/4/2023 DARIN LAM

Contact Information

Contractor Ind Construction Llc; Lic. No.: 937833-B 16430 VENTURA BLVD STE 208      ENCINO, CA 91436
Engineer Varela, Olivas, Benjamin; Lic. No.: S5714 6007 WASHINGTON BLVD      CULVER CITY, CA 90232

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/3/2024 Approved JESUS RODRIGUEZ
Sewer 4/3/2024 Approved JESUS RODRIGUEZ
Underground Mechanical 4/3/2024 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Partial Approval JESUS RODRIGUEZ
Insulation 5/3/2024 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 5/3/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 5/6/2024 Partial Approval TEMISTOCLES CAAL
Pre-Inspection 8/19/2024 Not Ready for Inspection JESUS RODRIGUEZ
Masonry Wall/Backfill 9/25/2024 Partial Approval JESUS PINEDA
PLUMBING-Rough 12/11/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Not Ready for Inspection BOBBY KEY
Special/Order Compliance 12/20/2024 Partial Inspection JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Approved JESUS PINEDA
Pre-Inspection 1/8/2025 Partial Inspection JESUS PINEDA
Interior/Exterior Lathing 2/3/2025 Partial Approval JESUS PINEDA
HVAC-Rough 2/7/2025 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 2/25/2025 Approved JESUS PINEDA
HVAC-Rough 2/25/2025 Approved JESUS PINEDA
PLUMBING-Rough 2/25/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 3/6/2025 Approved MICHAEL ALLEN
Green Building Rough 3/6/2025 Approved MICHAEL ALLEN
Shower Pan 3/13/2025 Corrections Issued JESUS PINEDA
Smoke Detectors 3/13/2025 Not Ready for Inspection JESUS PINEDA
Shower Pan 3/18/2025 No Access for Inspection MICHAEL ALLEN
Shower Pan 3/19/2025 Approved MICHAEL ALLEN
Insulation 3/20/2025 No Access for Inspection MICHAEL ALLEN
Interior/Exterior Lathing 3/20/2025 No Access for Inspection MICHAEL ALLEN
Insulation 3/24/2025 Corrections Issued MICHAEL ALLEN
Interior/Exterior Lathing 3/24/2025 No Access for Inspection MICHAEL ALLEN
Insulation 3/25/2025 Partial Approval MICHAEL ALLEN
Insulation 5/12/2025 Corrections Issued JAYLIN GRAVITTE
Drywall Nailing 5/19/2025 Approved JAYLIN GRAVITTE
Insulation 5/19/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 6/30/2025 Not Ready for Inspection JAYLIN GRAVITTE
Interior/Exterior Lathing 7/1/2025 No Access for Inspection JAYLIN GRAVITTE
Interior/Exterior Lathing 7/14/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 11/7/2025 Approved WILBER ROSALES
Service/Power Release 11/7/2025 Approved WILBER ROSALES
Final 12/5/2025 No Access for Inspection WILBER ROSALES
Green Building Final 12/5/2025 No Access for Inspection WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 12/5/2025 SGSOV Not Ready WILBER ROSALES
Smoke Detectors 12/5/2025 No Access for Inspection WILBER ROSALES
ELECTRICAL-Final 12/9/2025 Approved WILBER ROSALES
Final 12/9/2025 Corrections Issued WILBER ROSALES
Green Building Final 12/9/2025 Not Ready for Inspection WILBER ROSALES
HVAC-Final 12/9/2025 Corrections Issued WILBER ROSALES
PLUMBING-Final 12/9/2025 Corrections Issued WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Not Ready WILBER ROSALES
Smoke Detectors 12/9/2025 Not Ready for Inspection WILBER ROSALES
Special/Order Compliance 3/31/2026 Corrections Issued DAVID FEILER
Final 5/6/2026 OK to Issue CofO DAKOTA LOW
Green Building Final 5/6/2026 Approved DAKOTA LOW
HVAC-Final 5/6/2026 Approved DAKOTA LOW
PLUMBING-Final 5/6/2026 Approved DAKOTA LOW
SGSOV-Seismic Gas S/O Valve 5/6/2026 SGSOV Approved DAKOTA LOW
Smoke Detectors 5/6/2026 Approved DAKOTA LOW