1921 W 64TH ST 90047

Certificate Information: 1921 W 64TH ST 90047

Application / Permit
22014-30000-00621
Plan Check / Job No.
B22WL00589
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to rear of single family dwelling to create additional bedroom and expand existing bedroom. Add a new bathroom. Framing to comply with WFPP Standards.
Permit Issued
Issued on 6/27/2024
Issuing Office
South Los Angeles
Current Status
CofO Issued on 12/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 2/16/2022 ALFREDO JARA
Corrections Issued 2/16/2022 ALFREDO JARA
Applicant returned to address corrections 11/30/2023 SERGIO SILVA
Applicant returned to address corrections 4/25/2024 RICARDO RAMIREZ
Issued 6/27/2024 APPLICANT
No Progress 12/2/2025 DEROLD HAUFF
CofO in Progress 12/2/2025 DEROLD HAUFF
CofO in Progress 12/9/2025 BARRY HACHE
Permit Finaled 12/11/2025 DEROLD HAUFF
CofO Issued 12/11/2025 DEROLD HAUFF
Permit Finaled 12/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/13/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 7/13/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 7/26/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/6/2024 Corrections Issued MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 9/9/2024 Corrections Issued BRENDAN MORELLI
Special/Order Compliance 9/9/2024 Partial Approval NICHOLAS LOPEZ
Footing/Foundation/Slab 9/10/2024 Approved CRAIG DAVIS
Underground Mechanical 9/18/2024 Approved JOSE MACIAS
Wood Frame 9/18/2024 Partial Approval JOSE MACIAS
BUILDING-Rough-Frame 10/11/2024 Not Ready for Inspection JOHN QUINTANILLA
Green Building Rough 10/11/2024 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 10/11/2024 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Approved JOSE MACIAS
HVAC-Rough 10/17/2024 Approved JOSE MACIAS
Wood Frame 10/17/2024 Corrections Issued JOSE MACIAS
BUILDING-Rough-Frame 10/23/2024 Conditional Approval BRENDAN MORELLI
ELECTRICAL-Rough 10/23/2024 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 11/1/2024 Approved CRAIG DAVIS
Drywall Nailing 11/12/2024 Approved CRAIG DAVIS
Shower Pan 11/12/2024 Approved CRAIG DAVIS
Shower Pan 11/13/2024 Approved STUART CHAPMAN
BUILDING-Rough-Frame 12/13/2024 Approved CRAIG DAVIS
Final 12/13/2024 Corrections Issued CRAIG DAVIS
Green Building Final 12/13/2024 Approved CRAIG DAVIS
Green Building Rough 12/13/2024 Approved CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 12/13/2024 SGSOV Approved CRAIG DAVIS
Smoke Detectors 12/13/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 5/9/2025 Approved BARRY HACHE
Final 5/9/2025 Not Ready for Inspection BARRY HACHE
Green Building Rough 5/9/2025 Approved BARRY HACHE
Smoke Detectors 5/9/2025 Approved BARRY HACHE
Final 11/5/2025 Corrections Issued BARRY HACHE
Final 11/10/2025 Conditional Approval BARRY HACHE
Final 12/9/2025 OK to Issue CofO BARRY HACHE