3541 S BARRY AVE 90066
Certificate Information: 3541 S BARRY AVE 90066
- Application / Permit
- 22014-30000-00616
- Plan Check / Job No.
- B22WL00584
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and Addition to an (E) 1-Story S.F.D w/Attached Garage
- Permit Issued
- Issued on 8/10/2022
- Issuing Office
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | DAVID CASTILLO |
| Corrections Issued | 3/31/2022 | DAVID CASTILLO |
| Quality Review Completed | 4/13/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 6/14/2022 | DAVID CASTILLO |
| Plan Check Approved | 6/22/2022 | DAVID CASTILLO |
| Issued | 8/10/2022 | APPLICANT |
| Building Plans Picked Up | 8/12/2022 | APPLICANT |
| CofO in Progress | 8/24/2023 | JESUS PINEDA |
| Permit Finaled | 9/5/2023 | DANIEL ORRANTE |
| CofO Issued | 9/5/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/5/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2022 | JOSE HERNANDEZ |
| Low Impact Development | Cleared | 6/7/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 6/8/2022 | JENSON LEE |
| GPI Written Notices | Cleared | 6/14/2022 | CHIHARU SUZUKI |
| Grading Pre-Inspection | Cleared | 6/14/2022 | DAVID CASTILLO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bongolan,, Resur Galzote; Lic. No.: L8173 | 2139 PINECREST DR ALTADENA, CA 91001 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/24/2022 | Approved | ANDREW NAVE |
| Deputy Drilled-In Anchors | 10/20/2022 | Conditional Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 10/24/2022 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/24/2022 | Approved | OGANES TARAKHCHYAN |
| Grounding or Bonding | 10/24/2022 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 11/23/2022 | Partial Approval | JOHNNY MIRANDA |
| Sewer | 11/23/2022 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 11/23/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 12/14/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 2/15/2023 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2023 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 3/20/2023 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 3/20/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 3/20/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 3/20/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/20/2023 | Approved | JOHNNY MIRANDA |
| Wood Frame | 3/20/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/24/2023 | Partial Approval | CLAYTON GRAHAM |
| Shower Pan | 3/24/2023 | Approved | CLAYTON GRAHAM |
| Insulation | 3/31/2023 | Partial Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 4/4/2023 | Approved | KENNETH NAGLE |
| Green Building Rough | 4/4/2023 | Approved | KENNETH NAGLE |
| Insulation | 4/4/2023 | Approved | KENNETH NAGLE |
| Drywall Nailing | 4/10/2023 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 5/8/2023 | Approved | JOHNNY MIRANDA |
| Gas Test | 5/26/2023 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 5/26/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Final | 8/1/2023 | Corrections Issued | JESUS PINEDA |
| Service/Power Release | 8/1/2023 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 8/4/2023 | Approved | JESUS PINEDA |
| Service/Power Release | 8/4/2023 | Approved | JESUS PINEDA |
| Smoke Detectors | 8/4/2023 | Approved | JESUS PINEDA |
| Final | 8/23/2023 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 8/23/2023 | Approved | JESUS PINEDA |
| HVAC-Final | 8/23/2023 | Approved | JESUS PINEDA |
| PLUMBING-Final | 8/23/2023 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/23/2023 | SGSOV Approved | JESUS PINEDA |