3279 S CABRILLO BLVD 90066
Certificate Information: 3279 S CABRILLO BLVD 90066
- Application / Permit
- 22014-30000-00577
- Plan Check / Job No.
- B22WL00546
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition to an (e) 1-story S.F.D. w/ new attached garage. entire building being removed except 3' foundation
- Permit Issued
- Issued on 8/19/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | GARO TELMI |
| Corrections Issued | 3/11/2022 | GARO TELMI |
| Quality Review Completed | 3/18/2022 | KEN GILL |
| Building Plans Picked Up | 3/23/2022 | APPLICANT |
| Applicant returned to address corrections | 5/12/2022 | GARO TELMI |
| Applicant returned to address corrections | 8/11/2022 | GARO TELMI |
| Plan Check Approved | 8/18/2022 | GARO TELMI |
| Issued | 8/19/2022 | APPLICANT |
| CofO in Progress | 8/23/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 8/29/2023 | DANIEL ORRANTE |
| CofO Issued | 8/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 4/21/2022 | LOUIS ORTEGA |
| Low Impact Development | Cleared | 4/22/2022 | SARAH YOUSSEF |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2022 | STEVEN JIN |
| Permit | Cleared | 4/30/2022 | STEVEN JIN |
| Roof/Waste drainage to street | Cleared | 4/30/2022 | STEVEN JIN |
| Sewer availability | Cleared | 4/30/2022 | STEVEN JIN |
| Trees in Parkway | Cleared | 6/17/2022 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 8/11/2022 | MATTHEW JENKINS |
| Grading Pre-Inspection | Cleared | 8/11/2022 | MATTHEW JENKINS |
| Hold | Cleared | 9/23/2022 | PRISCILLA RUIZ |
| Hold | Cleared | 10/6/2022 | MARIA VENDIVIL |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/27/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Pre-Inspection | 10/3/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/11/2022 | Partial Approval | HERBERT GIRON |
| Deputy Reinf. Concrete | 10/25/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 10/25/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/25/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 10/27/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 11/22/2022 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 11/22/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 12/16/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Sewer | 12/19/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| Sewer | 12/21/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Wood Construction | 1/19/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/1/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 2/1/2023 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Final | 2/8/2023 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 2/8/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/21/2023 | Approved | EVAN COOPER |
| Shower Pan | 2/21/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 3/7/2023 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 3/7/2023 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 3/21/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 3/28/2023 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 3/31/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 3/31/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 3/31/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 3/31/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 4/7/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/12/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 6/30/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 7/11/2023 | Approved | JESUS RODRIGUEZ |
| Gas Test | 7/17/2023 | Approved | RICHARD STEINBACH |
| PLUMBING-Final | 7/17/2023 | Corrections Issued | RICHARD STEINBACH |
| ELECTRICAL-Final | 8/2/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 8/2/2023 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 8/2/2023 | Approved | JESUS RODRIGUEZ |
| Final | 8/17/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 8/17/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/17/2023 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 8/17/2023 | Approved | HERBERT GIRON |
| Final | 8/22/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/22/2023 | SGSOV Approved | JESUS RODRIGUEZ |