11827 W WAGNER ST 90230

Certificate Information: 11827 W WAGNER ST 90230

Application / Permit
22014-30000-00570
Plan Check / Job No.
B22WL00541
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1st and 2nd floor with roof deck addition, remodel to (E) S.F.D.
Permit Issued
Issued on 5/25/2022
Issuing Office
Current Status
CofO Issued on 12/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 HOOMAN HAJIZADEH
Corrections Issued 3/3/2022 HOOMAN HAJIZADEH
Quality Review Completed 3/14/2022 CHIHARU SUZUKI
Plan Check Approved 5/13/2022 HOOMAN HAJIZADEH
Issued 5/25/2022 APPLICANT
Building Plans Picked Up 5/27/2022 APPLICANT
CofO in Progress 12/5/2023 RICHARD STEINBACH
Permit Finaled 12/7/2023 DANIEL ORRANTE
CofO Issued 12/7/2023 DANIEL ORRANTE
Permit Finaled 12/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 4/1/2022 TA ANH
Roof/Waste drainage to street Cleared 4/14/2022 JOSE HERNANDEZ
Sewer availability Cleared 4/20/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 4/23/2022 JOSE HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/28/2022 Partial Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 9/14/2022 Corrections Issued JESUS RODRIGUEZ
Pre-Inspection 9/14/2022 Not Ready for Inspection JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/4/2022 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 10/4/2022 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 11/10/2022 Partial Approval HERBERT GIRON
Deputy Steel/Welding 11/16/2022 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/17/2022 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 11/18/2022 Corrections Issued JESUS RODRIGUEZ
Deputy Steel/Welding 12/16/2022 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/27/2022 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/27/2022 Partial Approval JESUS RODRIGUEZ
Special/Order Compliance 12/27/2022 Partial Inspection CLAYTON GRAHAM
Deputy Wood Construction 2/7/2023 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Partial Approval JESUS RODRIGUEZ
Green Building Rough 3/28/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 3/28/2023 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 3/28/2023 Corrections Issued JESUS RODRIGUEZ
Reinforced Masonry Frame 3/28/2023 Not Ready for Inspection JESUS RODRIGUEZ
Sewer 3/28/2023 Approved JESUS RODRIGUEZ
Underground Mechanical 3/28/2023 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 4/13/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/12/2023 Not Ready for Inspection JESUS RODRIGUEZ
Sewer 5/12/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 5/30/2023 Approved JESUS RODRIGUEZ
Green Building Rough 5/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 5/30/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/30/2023 Approved JESUS RODRIGUEZ
Structural Steel Frame 5/30/2023 Conditional Approval JESUS RODRIGUEZ
Insulation 6/6/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 6/6/2023 Approved JESUS RODRIGUEZ
Shower Pan 6/6/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 6/13/2023 Approved JESUS RODRIGUEZ
Green Building Rough 6/13/2023 Approved JESUS RODRIGUEZ
Gas Test 9/7/2023 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 9/7/2023 Not Ready for Inspection JESUS RODRIGUEZ
Deputy Wood Construction 9/11/2023 Conditional Approval RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 9/18/2023 SGSOV Approved JESUS RODRIGUEZ
ELECTRICAL-Final 10/3/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 10/3/2023 Approved JESUS RODRIGUEZ
HVAC-Final 10/3/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 10/3/2023 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 10/3/2023 Not Ready for Inspection JESUS RODRIGUEZ
Smoke Detectors 10/3/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 10/12/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 10/12/2023 Approved JESUS RODRIGUEZ
Final 10/12/2023 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 10/12/2023 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Final 10/12/2023 Approved JESUS RODRIGUEZ
Service/Power Release 10/12/2023 Not Ready for Inspection JESUS RODRIGUEZ
Structural Steel Frame 10/12/2023 Approved JESUS RODRIGUEZ
Final 11/29/2023 Conditional Approval JESUS RODRIGUEZ
HVAC-Final 11/29/2023 Approved JESUS RODRIGUEZ
Service/Power Release 11/29/2023 Approved JESUS RODRIGUEZ